Thornton Greener Grid Park, Thornton, Melbourne, York, YO42 4RZ (5 components)

BESS project to be installed within a future Greener Grid Park.

Active • 2028-29 (T-4), 2025-26 (T-1)
214.86 MW
Thorpe Marsh Ash Fields Ash Fields Road off Marsh Lane Thorpe in Balne/Barnby Dun Doncaster DN6 0EA (11 components)
• New-build generating CMU comprising battery storage and associated plant to be constructed on brownfield land at Thorpe Marsh, Yorkshire. Metering of output is Net of auxillary load.
• New-build generating CMU comprising battery storage and associated plant to be constructed on brownfield land at Thorpe Marsh, Yorkshire. Metering of output is Net of auxillary load.
Active • 2028-29 (T-4), 2027-28 (T-4)
627.45 MW
Tillingdown Lane, Caterham, CR3 7JA (4 components)
• A 12MW Distribution Connected Battery Energy Storage System
• A Distribution Connected Battery Energy Storage System
Active • 2028-29 (T-4)
15.04 MW
Toddington Road, Harlington, Central Bedfordshire, England, LU5 6LD, United Kingdom (1 component)

The proposed battery plant would consist of a number of new highly efficient battery storage units plus ancillary equipment.

Active • 2027-28 (T-4)
92.03 MW
Two Parcels Of Land Lying To The North West And South West Of Farm Road, Brackley NN13 7EB (3 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4), 2025-26 (T-1)
0.26 MW
Tyrant Farm, Treowen, Newbridge, Newport, NP11 3BS (2 components)

New Build Battery Storage Facility

Active • 2028-29 (T-4)
10.44 MW
Unit 1-2, Merrivale Road, Exeter Road Industrial Estate, Okehampton, EX20 1UD (3 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4), 2025-26 (T-1)
0.27 MW
Unit 1 Guildford Road Industrial Estate Hayle TR27 4QZ (2 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4), 2025-26 (T-1)
0.16 MW
Wadsworth Farm, Toronto, Bishop Auckland DL14 7RL (4 components)
• A 50MW Distribution Connected Battery Energy Storage System
• A Distribution Connected Battery Energy Storage System
Active • 2028-29 (T-4)
62.68 MW
Water Pumping Station, Watson Road, MK42 6BL (2 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2027-28 (T-4), 2024-25 (T-1)
0.05 MW
Water Tower, Knight Street, Pinchbeck, Spalding, PE11 3XD (2 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2027-28 (T-4), 2024-25 (T-1)
0.05 MW
West Marsh Road Spalding Lincolnshire PE11 3BB (3 components)
• A new battery storage system comprising batteries, containers, inverters, control systems and associated balance of plant. This will be constructed on brownfield land in Spalding, Lincolnshire. Metering of output is Net of auxiliary load.
• A new open cycle power station comprising gas turbines and associated balance of plant. This is being constructed on brownfield land in Spalding, Lincolnshire. Metering of output is Net of auxillary load.
Active • 2024-25 (T-4), 2022-23 (T-4) ...