Winnington CHP Winnington Lane Winnington Northwich Cheshire CW8 4GX (39 components)
• Continuously operating, maximum output GE gas turbine driving a 47.020MVA Alstom generator at 0.85 power factor.
• Continuously operating, maximum output GE gas turbine driving a 47.020MWA Alstom generator at 0.85 power factor.
• Continuously operating, variable output Man Diesel Turbo single pass-out back pressure turbine driving a 19.300 MVA TD Power Systems generator at 0.85 power factor.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
232.80 MW
The Long Barrow, Willesborough, Ashford, Kent. TN24 0GP (20 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2026-27 (T-4), 2022-23 (T-4) ...
9.52 MW
Pye Bridge Industrial Estate, Somercotes, Alfreton, DE55 4NX (14 components)
• Additional reciprocating gas engines running on natural gas returned to service
• Reciprocating gas engines running on natural gas
Active • 2026-27 (T-4), 2024-25 (T-1) ...
25.06 MW
Newton Aycliffe CO Durham DL5 6EA (24 components)
• Existing Gas Engine
• This is a long standing existing Gas Engine unit on land within a manufacturing site.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
27.91 MW
Mersey Wharf Business Park, Dock Road South, Bromborough Pool, Wirral, Merseyside, CH62 4SU (16 components)
• 16 MW power plant comprising gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
• Gas reciprocating engine
Active • 2028-29 (T-4), 2027-28 (T-4) ...
59.49 MW
Land and Buildings Known as Teres House Copse Road And Land Lying to the North of East Denham Way Fleetwood FY7 7NY (21 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear

Active • 2027-28 (T-4), 2026-27 (T-4) ...
8.09 MW
Land Adjacent to Stobarts Logistics Off Branthwaite Road Lillyhall Workington Cumbria CA14 4ED (21 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear

Active • 2028-29 (T-4), 2027-28 (T-4) ...
21.23 MW
Greengate Works Power Station, Sutton Heath Road or Burtonhead Road, St Helens, WA9 5DS (15 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
28.28 MW
Dogsthorpe Landfill Site Welland Road Peterborough Cambridgeshire PE1 3TD (7 components)
• 2 gas reciprocating engines with a combined export output of approximately 2MW. The generating equipment is connected to the distribution network via an import/export meter.
• Gas reciprocating engines
Active • 2028-29 (T-4), 2027-28 (T-4) ...
11.44 MW
Chesterfield Road, Swallownest, Sheffield, S26 4SX (3 components)
• Gas fired reciprocating engines
• New Build Generating CMU comprising of battery storage and associated plant.
Active • 2026-27 (T-4), 2021-22 (T-4)
2.84 MW
Chase Hill Road Killingholme North Lincolnshire DN40 3LU (36 components)
• Killingholme Module 1 converted to open cycle operation
• Killingholme Module 2 converted to open cycle operation
• Killingholme Module 2 converted to open cycle operation please see letter uploaded to metering section that explains determination of three highest HH
Active • 2028-29 (T-4), 2026-27 (T-4) ...
2096.76 MW
Cavendish Rd Stevenage SG1 2ET UK (23 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 8MW.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
22.64 MW
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (44 components)
• The CMU component is a combined cycle gas turbine
• This CMU (CARRI3) will be formed of multiple gas reciprocating units controlled centrally & exporting to the Distribution system.
• This CMU (CGTN_3) will be formed of multiple gas reciprocating units controlled centrally & exporting to the Distribution system.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3471.17 MW
Bond Avenue Bletchley Milton Keynes MK1 1JJ (27 components)

The CMU component comprises of three 2MW Reciprocating Gas Engines

Active • 2028-29 (T-4), 2027-28 (T-4) ...
28.70 MW
4 Finway Road Hemel Hempstead HP2 7PT (21 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW

Active • 2027-28 (T-4), 2026-27 (T-4) ...
14.23 MW
1A Elms Farm Industrial Estate Edison Road Bedford Bedfordshire MK41 0HU (22 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW.

Active • 2027-28 (T-4), 2026-27 (T-4) ...
14.23 MW