10 unique locations (377 components)

WEMBLEY ENERGY CENTRE, HARBUTT ROAD, OFF ENGINEERS WAY, WEMBLEY, LONDON, HA9 0NH (8 components)
• A gas engine CHP site providing hot water to a local district heating network
• Didcot B5 - CCGT MSID: 4055
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2026-27 (T-4), 2025-26 (T-4) ...
17.68 MW
Staythorpe Power Station Staythorpe Newark Nottinghamshire NG23 5PS (60 components)
• Staythorpe 1 - CCGT MSID: 7210
• Staythorpe 2 - CCGT MSID: 7210
• Staythorpe 4 - CCGT MSID: 7210
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6050.24 MW
Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom (12 components)
• CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S26G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW.
• Didcot B6 - CCGT MSID: 4055
Active • 2028-29 (T-4), 2027-28 (T-4) ...
762.63 MW
RWE Cogen UK (Hythe) Ltd Charleston Road Hardley Hythe Southampton SO45 3BP (5 components)
• Lithium Ion battery storage system capable of charging, storing and discharging electricity. Land at Stevensons Farm, Arterial Road, Nevendon, Essex SS14 3JH.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• On-site existing CHP generating unit
Active • 2026-27 (T-4), 2024-25 (T-4) ...
41.27 MW
Ferrybridge Power Station, Stranglands Lane, Knottingley, West Yorkshire, WF11 8SQ (125 components)
• Aux. load separately metered
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW
• GT8
Active • 2026-27 (T-4), 2025-26 (T-4) ...
31264.81 MW
Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom (13 components)
• BM Unit T_FFES-3 at Ffestiniog Power Station (Pumped Storage)
• Unit 5 is a Cogenation unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG-19, EMD-19 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power and steam generation units on site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02). Gross 3 HH av. peak generation from Unit 5 on separate days = 141.040 MW At these three HH times, aux load on Unit 5 = 2.597 MW Net generation from Unit 5 = 138.443 MW
• Unit 5 is a Cogeneration unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG244 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power generation units on the site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment, the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02).
Active • 2028-29 (T-4), 2027-28 (T-4) ...
382.93 MW
Drayton Garden Village CHP, Porters Way, Hillingdon, Greater London, UB7 9AA (15 components)
• A gas engine CHP site providing hot water to a local district heating network
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Pembroke 11 - CCGT MSID: 7237
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1.71 MW
Cowes Power Station Kingston Road East Cowes Isle of Wight PO32 6JS (37 components)
• Cowes 1 - OCGT, fuel is distillate MSID: 4548
• Cowes 2 - OCGT, fuel is distillate MSID: 4548
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
498.22 MW
Aberthaw Power Station The Leys Aberthaw Barry Mid Glamorgan CF62 4ZW (90 components)
• E1000 CHP
• Existing CCGT
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2026-27 (T-4), 2024-25 (T-4) ...
2435.45 MW
Loading map...