Home Grok GrokAsk Grok (Beta) Technologies Companies Locations Map Explorer FAQ Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

CHP and autogeneration

105 unique locations (1224 components) - Page 1 of 5

Active MW: 35388.22 MW
Inactive MW: 1729.46 MW
Woodhouse Energy Centre, A. Pearson and Sons? Nursery, Alderley Edge, SK9 7UW (9 components) Geocoding Needed
β€’ The CMU Component will have a connection capacity of 3.298MW net of 46kW auxiliary load. Gas-fired reciprocating engine will be the technology used.
β€’ The CMU Component will have a connection capacity of 3.376MW. Gas-fired reciprocating engine will be the technology used.
β€’ The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
20.05 MW
Wood End, Stocks Lane, Over Peover, Knutsford WA16 9EZ (18 components) Geocoding Needed
β€’ 2MW gas CHP engine in a horticultural environment
β€’ One 1.5 MW gas CHP engine in a horticultural environment
β€’ One 2MW gas CHP engine in a horticultural environment
CHP and autogeneration Combined Heat and Power (CHP) FLEXITRICITY LIMITED Existing Generating CMU FLEX110 FLEX110 +5 more WA16
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
25.64 MW
374.81 MW
Winnington CHP, Winnington Lane, Winnington, Northwich, Cheshire, CW8 4GX (28 components) Geocoding Needed
β€’ Continuously operating, maximum output GE gas turbine driving a 47.020MVA Alstom generator at 0.85 power factor.
β€’ Continuously operating, maximum output GE gas turbine driving a 47.020MWA Alstom generator at 0.85 power factor.
β€’ Continuously operating, variable output Man Diesel Turbo single pass-out back pressure turbine driving a 19.300 MVA TD Power Systems generator at 0.85 power factor.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
462.46 MW
Westland Nurseries (Offenham) Ltd., Station Road, Offenham, Evesham, Worcestershire, WR11 8LW (12 components) Geocoding Needed
β€’ Gas CHP in a horticultiral environment providing heat for crop growth
β€’ One asset 1.5MW CHP engine in a horticultural environment with no auxiliary load.
CHP and autogeneration Combined Heat and Power (CHP) FLEXITRICITY LIMITED Existing Generating CMU FLEX110 FLEX110 +2 more WR11
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
16.62 MW
Westexe, Tiverton, Devon, EX16 5LL (6 components) Geocoding Needed

2026 kW CHP unit

Active β€’ 2026-27 (T-4), 2025-26 (T-4) ...
9.10 MW
WEPA Bridgend Paper Mill, Llangynwyd, Mid Glamorgan, South Wales CF34 9RS (6 components) Geocoding Needed

Existing Generation on existing site - CHP

Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
39.32 MW
WEMBLEY ENERGY CENTRE, HARBUTT ROAD, OFF ENGINEERS WAY, WEMBLEY, LONDON, HA9 0NH (6 components) Geocoding Needed

A gas engine CHP site providing hot water to a local district heating network

Combined Heat and Power (CHP) E.ON UK PLC Existing Generating CMU CE_Aggregated 3 CE_Aggregated 3 +1 more HA9
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
5.96 MW
Warrington Sustainable Energy LTD, Skyline Drive, Warrington, WA5 3TP (11 components) Geocoding Needed

Warrington Existing Site CHP

Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
13.64 MW
7.20 MW
7.25 MW
Treviscoe Dryer, Little Treviscoe, St. Austell, PL26 7QN (9 components) Geocoding Needed
β€’ Gas CHP in St. Austell
β€’ Gas fired CHP unit
Combined Heat and Power (CHP) KIWI POWER LTD Existing Generating CMU KPEG55 PL26
Active β€’ 2026-27 (T-4), 2025-26 (T-4) ...
13.60 MW
Tower Nurseries Netherhall Road Roydon Essex CM19 5JP (10 components) Geocoding Needed
β€’ Gas CHP engines 1.5MW and 1.48MW. Primary fuel type = Natural Gas
β€’ Gas engines in commercial horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations
Active β€’ 2028-29 (T-4), 2026-27 (T-4) ...
13.42 MW
Tower Nurseries Netherhall Road Roydon Essex CM19 5JP (10 components)

Gas engines in commercial horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations (3)

Active β€’ 2028-29 (T-4), 2026-27 (T-4) ...
5.59 MW
Thirsk Factory, Dalton Airfield, Topcliffe, Thirsk, YO7 3HE. (5 components) Geocoding Needed

1.280MW CHP

Active β€’ 2026-27 (T-4), 2025-26 (T-4) ...
4.65 MW
The Ridgeway, Enfield, Middlesex, EN2 8JL (10 components) Geocoding Needed
β€’ On-site CHP - existing generating unit The Ridgeway Enfield, Middlesex EN2 8JL OS Grid Reference: TQ 312 980
β€’ On-site CHP - existing generating unit The Ridgeway Enfield, Middlesex EN2 8JL OS Grid Reference: TQ 312 980
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
5.74 MW
Tees Valley Nursery, The Moat, Belasis Hall, TS23 4ED (21 components) Geocoding Needed
β€’ The CMU component TEES01 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
β€’ The CMU component TEES02 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
40.32 MW
St Andrews CHP, Devons Road, Bromley by Bow, London, E3 3BF (9 components) Geocoding Needed

A gas engine CHP site providing hot water to a local district heating network

Combined Heat and Power (CHP) E.ON UK PLC Existing Generating CMU CE_Aggregated CE_Aggregated +4 more E3
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
7.48 MW
Staithes Road, Preston, Hull, HU12 8TB (17 components) Geocoding Needed
β€’ CHP Unit Located at Staithes Road, Preston, Hull, HU12 8TB
β€’ Gas fired CHP unit
β€’ Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
18.11 MW
Stainland Boardmill, Holywell Green, Halifax, HX4 9PY (3 components) Geocoding Needed

Gas Fired CHP

Combined Heat and Power (CHP) E.ON UK PLC New Build Generating CMU SON_CHP SON_CHP HX4
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
8.78 MW
SOUTH STAFFORDSHIRE WATER PLC, Hampton Loade Treatment Works, Hampton Loade, Bridgnorth, WV15 6HD (10 components) Geocoding Needed

Existing Generation on existing site - CHP

Combined Heat and Power (CHP) GRIDBEYOND LIMITED Existing Generating CMU Rejected WV15
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
22.71 MW
Solvay, Trinity St, Oldbury, B69 4LW (6 components) Geocoding Needed

Existing Generation on existing site - CHP

Combined Heat and Power (CHP) GRIDBEYOND LIMITED Existing Generating CMU Rejected B69
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
6.66 MW
Smurfit Kappa SSK, Mount Street, Nechells, Birmingham B7 5RE (11 components) Geocoding Needed
β€’ 8.300MW Gas Turbine installation
β€’ 8.3MW Gas Turbine installation
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
46.90 MW
Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS, United Kingdom (12 components) Geocoding Needed
β€’ CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S23G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
β€’ CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S24G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
β€’ CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S26G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
453.78 MW
Loading map...
Showing 25 locations