CENTRICA BUSINESS SOLUTIONS UK OPTIMISATION LIMITED

17 unique locations (464 components)

Active MW: 881.00 MW
Inactive MW: 4153.24 MW
1 Rivington Rd, Preston Brook, Runcorn WA7 3DP, United Kingdom (13 components)
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• On-site existing CHP generating unit
• The proposed power plant would consist of a number new highly efficient gas fired generating units plus ancillary equipment. Each genset is based on advanced reciprocating engine technology.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2 South Wardpark Place, Wardpark, Cumbernauld, Glasgow, North Lanarkshire, G67 3HX (35 components)
• EV charging at residential premises
• Operational Reciprocating Engine
• Operational gas reciprocating engine.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Asda Gosforth Wansbeck Road, Wansbeck Road South Fawdon, Newcastle, NE3 3HQ (10 components)
• Gas Turbine Cogeneration Unit GT3
• Load curtailment
• Load curtailment from refridgeration
Active • 2028-29 (T-4), 2025-26 (T-4) ...
British Steel Limited, Administration Building, Brigg Road, Scunthorpe, North Lincolnshire, DN16 1XA (46 components)
• Hamms Hall - Existing Site CHP
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• existing CHP on site
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EnviroWales - Ebbw Vale - Site 1, Plateaux 1 & 2 Rassau Industrial Estate Ebbw Vale Blaenau Gwent NP23 5SD (16 components)
• 48MW Battery Energy Storage facility
• Gas peaking reciprocating engine
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2028-29 (T-4), 2024-25 (T-4) ...
Errochty Power Station, Tummel Bridge, Pitlochry, PH16 5NT (27 components)
• Generating Unit 1
• Generating Unit 2
• Generating Unit 3
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Fowler Welch - Site 2, W Marsh Rd, Spalding PE11 2HR, UK (22 components)
• Gas turbine generator
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• The CMU Component reduces import demand by turning off equipment and other non-essential loads.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Fowler Welch - Site 3, W Marsh Rd, Spalding PE11 2HR, UK (23 components)
• A 10MW new build gas generating station..
• CMU consisting of multiple reciprocating engines and alternators
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Land on the east side of Cowpen Bewley Road, Billingham,  TS23 4ED (26 components)
• Gas peaking reciprocating engine
• On-site CHP - existing generating unit Maesgwyn Farm, Chirk, Wrexham, LL14 5NT SJ 284 383
• Reciprocating genset
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Medway Power Station, Rochester, Medway, ME3 0AG (29 components)
• A gas fuelled generating station.
• Genset 3
• Medway CCGT
Active • 2028-29 (T-4), 2027-28 (T-4) ...
MGH Property Services Limited, Laurels Farm, Hatherton, Nantwich, CW5 7PW (16 components)
• A 6.000MW Battery Energy Storage System to be installed at Gatwick Electric Forecourt
• Didcot 3 OCGT - Power factor used for conversion of kVA to MW is 1 . Fuel type is distillate MSID: 4032
• Nantwich Existing Site CHP
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Monkerton Energy Centre, Tithebarn Lane, Exeter, Devon, EX1 3RH (8 components)
• A gas engine CHP site providing hot water to a local district heating network
• Battery storage
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Power Station Road Isle of Grain Rochester ME3 0AR (69 components)
• Grain B CCGT Unit 6 Grain B power station provides heat to the Grain LNG regasification facility.
• OCGT from Grain U1. Fuel is Diesel as specified in BS EN590
• OCGT from Grain U4. Fuel is Diesel as specified in BS EN590
Active • 2028-29 (T-4), 2027-28 (T-4) ...
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 4 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
The Canalside, Marsh Lane, off Showground Road, Bridgwater, Somerset, TA6 6LQ (20 components)
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• New build windfarm.
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Weetabix, Station Rd, Burton Latimer, Kettering NN15 5JR, United Kingdom (27 components)
• Component has yet to be procured.
• EnerG 1000 CHP
• On-site CHP - existing generating unit
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW (12 components)
• A gas engine CHP site providing hot water to a local district heating network, as well as providing some power direct via private wire to a local hotel
• Didcot 2 OCGT - Power factor used for conversion of kVA to MW is 1 . Fuel type is distillate MSID: 4032
• The CMU Component will have a connection capacity of 3.298MW net of 46kW auxiliary load. Gas-fired reciprocating engine will be the technology used.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Loading map...
Showing 17 locations