Storage (Duration 4h)

18 unique locations (165 components)

Eggborough Power Station, Goole, East Yorkshire, DN14 0BS (49 components)
• New build Open Cycle Gas Turbine unit 5 at Eggborough Power Station (2)
• Battery Energy Storage System built on land at the former Eggborough Power Station (Unit 3)
• Battery Energy Storage System built on land at the former Eggborough Power Station (Unit 4)
• ... and 1 more unique description
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2549.84 MW
Eccles Birgham Farm TD12 4LU (9 components)
• 400MW battery storage located near to the SPT Eccles substation, split into four BMU's
• 50MW battery storage located near to the SPT Eccles substation
• 50MW battery storage located near to the SPT Eccles substation.
• ... and 1 more unique description
Active • 2028-29 (T-4), 2027-28 (T-4) ...
197.82 MW
170.15 MW
adjacent to Kilmarnock South Substation KA1 3TN (12 components)

Lithium ion battery storage plant (2)

Active • 2026-27 (T-4), 2025-26 (T-1)
150.05 MW
Netherton Farm, Keith AB55 5PE (12 components)
• 200MW battery storage located near to the National Grid Blackhillock substation, split into two BMU's (2)
• 200MW battery storage located near to the National Grid Blackhillock substation, split into four BMU's
• 200MW battery storage located near to the National Grid Blackhillock substation, split into two BMU's.
• ... and 1 more unique description
Active • 2026-27 (T-4), 2025-26 (T-4) ...
124.49 MW
Land at Pond Farm, Pond Lane, Charlton, SN16 9DS (8 components)

A Battery Energy Storage System. (4)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
116.20 MW
adjacent to National Grid Stalybridge substation SK15 3DA (3 components)
• 150MW battery storage located near to the National Grid Stalybridge substation, split into two BMU's
• 75MW battery storage located near to the National Grid Stalybridge substation.
Active • 2027-28 (T-4), 2026-27 (T-4)
58.53 MW
East Tarelgin Farm, Ayr, KA6 6NF (4 components)
• 18.5MW/74MWh of BESS to be installed within a future Greener Grid Park.
• 50MW/100MWh of BESS to be installed within a future Greener Grid Park.
• BESS to be installed within a Greener Grid Park
Active • 2028-29 (T-4), 2026-27 (T-4) ...
39.02 MW
Land east of Bramford Substation, Bullen Lane, Bramford, IP8 4JH (3 components)

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation. (3)

Active • 2026-27 (T-4), 2025-26 (T-1) ...
22.99 MW
Land Adjacent to No 13 Westerton Road Keith, Moray, Scotland AB55 5FA (2 components)

50MW of BESS to be installed within existing Rotating Stabiliser site. (2)

Active • 2026-27 (T-4), 2025-26 (T-4)
8.48 MW
Dragons Lane, Moston, Sandbach, CW11 3QH (2 components)

12 MW Connection 48 MWh Distribution unit (2)

Active • 2026-27 (T-4), 2023-24 (T-1)
5.50 MW
School Power, Rochester Road, Wouldham, Rochester, ME1 3TS (4 components)
• CMU component consisting of multiple battery cells for electricity storage @ 11kV and the supply of electricity to the 11kV … (2)
• CMU consisting of multiple battery cells for electricity storage and the supply of electricity to the electricity grid (2)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
4.87 MW
Loading map...
Showing 18 locations