1 unique locations (8 components)

High Oak WTW, HIGH OAK WW, High Oak Road, Wicklewood, WYMONDHAM Norfolk, NR18 9QR (8 components)
• A new build 10MW battery storage facility. The construction of this new build generating CMU comprises site preparation; ground works for concrete raft foundations and cable trenching; installation of three containerised battery units; six inverter banks; associated 33kV transformer; switchgear and HV station.
• The CMU Component reduces import demand by turning on back up generation.
Inactive • 2021-22 (T-4), 2020-21 (T-4) ...