20 unique locations (182 components)

Bluehouse Farm, Newton Bewley, Billingham, Durham, TS22 5PW (3 components)

Battery storage located at Bluehouse Farm, Newton Bewley, Billingham, Durham, TS22 5PW with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing …

Active • 2028-29 (T-4)
0.11 MW
BRLR, land east of Redhouse electricity substation, Heatherywood Road, Kirkcaldy, Fife, KY1 3NW. (1 component)

Battery energy storage system (1c rating, NMC lithium ion) comprising eight inverters with nominal power output rating of 2.0MW each (16.0MW total). The connection capacity of the BESS has been …

Active • 2028-29 (T-4)
1.05 MW
Brook Hall Farm, North Bradley, Trowbridge, Wiltshire, BA14 9PT (3 components)

Battery storage located at Brook Hall Farm, North Bradley, Trowbridge, Wiltshire, BA14 9PT with a nameplate capacity of 0.800 MW. Connection capacity is calculated as the Average Output of the …

Active • 2028-29 (T-4)
0.11 MW
Cowley Substation Blackberry Lane Garsington Oxfordshire OX44 9BD (14 components)
• The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
• The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.
Active • 2024-25 (T-4), 2025-26 (T-4) ...
34.61 MW
Dairy Lane Westhamnett Chichester PO20 2BG (8 components)

4MW battery co-located with a solar farm

Active • 2024-25 (T-4), 2025-26 (T-4) ...
1.51 MW
Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG (9 components)
• 0.400MW of storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG
• Battery storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG with a nameplate capacity of 1.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Active • 2024-25 (T-4), 2025-26 (T-4) ...
2.67 MW
Heywood Grange, Dilhorne, Staffordshire, ST10 2PL (4 components)

Battery storage located at Heywood Grange, Dilhorne, Staffordshire, ST10 2PL with a nameplate capacity of 1.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU …

Active • 2026-27 (T-4), 2027-28 (T-4) ...
0.20 MW
Hungerford Farm, Winchfield, Hook, RG27 8SW (3 components)

Battery storage located at Hungerford Farm, Winchfield, Hook, RG27 8SW with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU …

Active • 2028-29 (T-4)
0.11 MW
Ipswich Road, Cardiff, CF23 9AQ (10 components)
• New build one-hour duration storage
• New build two-hour duration battery storage
Active • 2025-26 (T-4), 2026-27 (T-4) ...
41.79 MW
Land adjacent to Nursling Substation Station Road Nursling Southampton SO16 0AH (24 components)
• New build battery storage unit
• New build transmission connected battery storage unit comprising battery cells, DC switchgear, power conversion, AC voltage transformation and connection switchgear with protection
• battery storage unit
Active • 2023-24 (T-1), 2023-24 (T-4) ...
15.21 MW
Land at Greenfield Road, Clayhill Farm, Westoning, Bedford, MK45 5JD (19 components)

CMU comprising of battery storage and associated plant

Active • 2024-25 (T-1), 2025-26 (T-4) ...
50.46 MW
Land at Hall Farm, Northwold, Thetford, IP26 5LQ (6 components)

7.5MW, 1-hour duration battery energy storage system (BESS). BESS is being constructed alongside a co-located solar PV farm which it shares a grid connection with.

Active • 2025-26 (T-1), 2028-29 (T-4)
3.62 MW
Land North of Clayhill Farm, Westoning MK45 5JD (8 components)
• 1.200MW of storage located at Land North of Clayhill Farm, Westoning MK45 5JD
• Battery storage located at Land North of Clayhill Farm, Westoning MK45 5JD with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Active • 2024-25 (T-4), 2025-26 (T-4) ...
0.30 MW
Land To The South Of Rock Farm, Rocks Green, Ludlow, SY8 2DS (17 components)
• 17.315 MW installed capacity Battery Storage facility
• 19.6 MW Battery Storage facility
• 19.6 MW installed capacity Battery Storage facility with proven DSR capacity 19.083
Active • 2022-23 (T-4), 2023-24 (T-4) ...
4.68 MW
Larport Farm, Larport Lane, Dormington, Hereford, HR1 4EP (13 components)
• 19.500MW of battery storage located at Larport Farm, Larport Lane, Dormington, Hereford, HR1 4EP
• Battery storage located at Larport Farm, Larport Lane, Dormington, Hereford, HR1 4EP with a nameplate capacity of 19.500 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Active • 2024-25 (T-4), 2025-26 (T-4) ...
243.40 MW
Low Burntoft, Newton Bewley, Billingham, Durham, TS22 5PD (5 components)

Battery storage located at Low Burntoft, Newton Bewley, Billingham, Durham, TS22 5PD with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing …

Active • 2026-27 (T-4), 2027-28 (T-4) ...
0.26 MW
Redditch Generation Station, Windsor Road, Redditch, B97 6HE (2 components)
• Battery Storage Station
• Gas reciprocating engines as the generating unit.
Active • 2025-26 (T-4), 2028-29 (T-4)
26.22 MW
Roundswell Business Park, Barnstaple, Devon EX31 3TD (2 components)

Front of the Meter battery storage asset located in Devon.

Active • 2024-25 (T-1), 2028-29 (T-4)
0.70 MW
Stockbridge Storage Farm, Land Adjacent to B3049, Stockbridge Road, Winchester.SO22 5FP (16 components)
• 10.0MW Battery Storage facility located at Stockbridge Road, Winchester, Hampshire
• 8.179 MW Battery Storage facility located at Stockbridge Road, Winchester, Hampshire
Active • 2023-24 (T-4), 2024-25 (T-4) ...
20.07 MW
Sunrise House, Hulley Road, Macclesfield, Cheshire, SK10 2LP (15 components)
• 20.000MW of battery storage located at Sunrise House, Hulley Road, Macclesfield, Cheshire, SK10 2LP
• 20MW battery storage site
• Battery storage located at Sunrise House, Hulley Road, Macclesfield, Cheshire, SK10 2LP with a nameplate capacity of 20.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Active • 2024-25 (T-4), 2025-26 (T-4) ...
12.88 MW
Loading map...