Reciprocating engines

7 unique locations (163 components)

SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 4 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
LAND ON THE WEST SIDE OF MAIN ROAD, GRENDON, NORTHAMPTON, NN7 1JW. (Nearest postcode to grid reference: NN7 1JB). (16 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Battery Storage Plant
• Didcot 2 OCGT - Power factor used for conversion of kVA to MW is 1 . Fuel type is distillate MSID: 4032
Active • 2025-26 (T-4), 2024-25 (T-4) ...
102.46 MW
land north of The Brickmakers Arms, Woburn Road, Kempston, Bedfordshire, MK43 9AB (11 components)
• A 12MW containerised Energy Storage System (lithium ion batteries) with 1.5MW of storage capacity.
• A 12MW containerised Energy Storage System (lithium ion batteries) with 2 hours of storage capacity.
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2025-26 (T-4), 2025-26 (T-1) ...
15.25 MW
Galley Hill Road Waltham Abbey Essex EN9 2AG (25 components)
• Gas engines in commercial horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Redditch 20MW Gas Peaker Project
Active • 2028-29 (T-4), 2026-27 (T-4) ...
27.74 MW
EnviroWales - Ebbw Vale - Site 2, Plateaux 1 & 2 Rassau Industrial Estate Ebbw Vale Blaenau Gwent NP23 5SD (17 components)
• 16 MW power plant comprising gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2028-29 (T-4), 2025-26 (T-4) ...
12.93 MW
Bristol Royal Infirmary, Marlborough Hill, Bristol, BS2 8HW (13 components)
• 1 * 1.7MW diesel reciporcating engine
• 1 * 1.7MW diesel reciprocating engine
• New Build Combined Cycle Gas Turbine plant to be installed on designated land at the Drax Power Station site
Active • 2026-27 (T-4), 2025-26 (T-4) ...
10.19 MW
323 Avebury Boulevard, MILTON KEYNES MK9 2GA (16 components)
• 1.200MW BESS
• A coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-5.
• District heating implementation of two gas CHP engines with no auxilliary load
Active • 2026-27 (T-4), 2025-26 (T-4) ...
9.27 MW
Loading map...
Showing 7 locations