10 unique locations (387 components)

Manchester Rd, Carrington, Manchester M31 4TG (33 components)
• 2 x 2.5 MW gas fuelled generators installed on land east of Griffiths Road.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• The CMU component at Pikelaw Place is an energy storage system comprised of Lithium-ion batteries. The system will have a 10 MW export capacity and an import capacity of 10 MW.
Active • 2026-27 (T-4), 2024-25 (T-1) ...
12.59 MW
Little Barford Power Station Little Barford St Neots PE19 6YT (32 components)
• 49.9MW Lithium Ion Batteries and power conversion system installed in a compound at Chickerell Substation.
• Little Barford 1 CCGT MSID: 4052
• Little Barford 1 OCGT . fuel type is distillate MSID: 4052
Active • 2028-29 (T-4), 2026-27 (T-4) ...
3881.97 MW
Land just north of the railway line, High Middlefield Farm, Durham Road, Thorpe Thewles, TS21 3LS (4 components)
• A Battery Energy Storage System.
• Energy facility comprising of reciprocating engine sets and ancillary equipment.
• Gas peaking reciprocating engine
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Land at Stanhope Industrial Estate, Wharf Road, Standford-Le-Hope SS17 0EH (17 components)
• 10 x 2MW Gas fuelled generator units to be installed on designated land within a compound at Stanford le-hope
• 5 x 2MW Containerised High Speed Gas-fired reciprocating engines together with transformers, switchgear and associated control gear at Stanhope industrial Estate
• CMU consisting of multiple reciprocating engines and alternators
Active • 2025-26 (T-4), 2024-25 (T-4) ...
85.66 MW
Land at Model Farm, Frenchs Road, Walpole St. Andrew, Norfolk, PE14 7JE. (17 components)
• 1 x Containerised High Speed Gas-fired reciprocating engines with an output of 2.5MW together with transformers, switchgear and associated control gear
• 2026 kW CHP unit
• N/A
Active • 2025-26 (T-4), 2022-23 (T-4) ...
Greenfield Road, Westoning, Bedford, MK45 5JD (9 components)
• 10 x 1mw Battery Storage units to be installed on designated land at Greenfield Road - Connection offer is for 40mw which is split between CMUs - further detail in covering letter
• 6 x reciprocating engines
• A Battery Energy Storage System.
Active • 2025-26 (T-4), 2023-24 (T-4) ...
Fell View Farm, Preston Road, Grimsargh, Preston, PR2 5SD (13 components)
• 1.200MW of storage located at Fell View Farm, Preston Road, Grimsargh, Preston, PR2 5SD
• Battery storage located at Fell View Farm, Preston Road, Grimsargh, Preston, PR2 5SD with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
• CMU consisting of a gas reciprocating engine and alternator
Active • 2028-29 (T-4), 2025-26 (T-4) ...
1.70 MW
Eastfield Road, North Killingholme, Immingham, North Lincolnshire, DN40 3LW (79 components)
• CMU consisting of multiple gas reciprocating engines and alternators
• Energy facility comprising of reciprocating engine sets.
• TBC
Active • 2026-27 (T-4), 2024-25 (T-4) ...
7.28 MW
Component has yet to be procured. (154 components)
• BM unit T_DINO-1 at Dinorwig Power Station (Pumped Storage)
• Component has yet to be procured.
• N/A
Active • 2025-26 (T-4), 2024-25 (T-4) ...
252.48 MW
Aberaman Industrial Estate (South Bound), Aberaman, Nr Aberdare, Rhondda Cynon Taff, CF44 6DA (29 components)
• 1.200MW of storage located at Land North of Clayhill Farm, Westoning MK45 5JD
• New build transmission connected battery storage site
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
18.90 MW
Loading map...
Showing 10 locations