37 unique locations (202 components) - Page 1 of 2

Yard at Windsor Street, Windsor Street, Oldham, OL1 4AQ (2 components)
• 10 x 2MW gas reciprocating engines used for power generation, with associated infrastructure.
• Gas fuelled CHP generation plant
Inactive • 2022-23 (T-3), 2020-21 (T-4)
Wytch Farm, Wareham BH20 5JR (6 components)

Two gas turbines (CX501-KB7) rated at 5.3MW each.

Inactive • 2021-22 (T-4), 2019-20 (T-1) ...
TWINYARDS FARM HUTHWAITE LANE ALFRETON DE55 5HW (3 components)

NEW BUILD GAS FUELLED GENERATION STATION

Inactive • 2019-20 (T-1)
The Yard, Holme Road, Stoney Holme, Burnley, BB12 0BJ (2 components)
• 3 x 2MW gas reciprocating engines used for power generation, with associated infrastructure
• Processing station installed on site will provide real time consumption data for the site which will be recorded and aggregated with readings from the rest of the CMU components.
Inactive • 2023-24 (T-4), 2022-23 (T-4)
5.70 MW
RWE Generation UK plc Ferrybridge A Workshop Site Old Great North Road Knottingley WF11 8PR (1 component)

A CMU will be formed of an Open Cycle Gas Turbine unit.

Inactive • 2022-23 (T-4)
RWE Generation UK plc Ferrybridge A Workshop Site Old Great North Road Knottingley WF11 8PR (1 component)

A CMU will be formed of an Open Cycle Gas Turbine unit.

Inactive • 2022-23 (T-4)
Progress Power Station, Eye Airfield, Diss, Suffolk, IP23 7HE (5 components)
• A new 299MW Open Cycle Gas Turbine (OCGT) power peaking plant
• New reciprocating genset in acoustic enclosure
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Mill Lane, Kirkby in Ashfield, NG17 9LG (3 components)

5 x2MW gas reciprocating engines used for power generation, with associated infrastructure.

Inactive • 2019-20 (T-1)
M & D Business Park, Burtonhead Road, St. Helens, WA9 5EA (1 component)

Ratcliffe U4 auxiliary gas turbine. Note this Generating Unit is fuelled on Gas Oil as specified by BS2869 Class A2

Inactive • 2023-24 (T-4)
Marsh Green Idustrial Park, Marsh Barton Trading Estate, Exeter, Devon, EX2 8NY (9 components)
• Existing OCGT.
• Gas CHP servicing the electricity and heat requirements for Aldergrove Nursery, one of the horticultural sites which trades at Flavourfresh Salads. All generation unit capacities are nominal and allow for site-specific variations.
• The auxiliary load is minimal (1MW) and have been removed from the metering assessment when calculating the maximum generating output
Inactive • 2022-23 (T-3), 2021-22 (T-4) ...
Main Site Energy Centre Main Road Hale Common Arreton Newport Isle of Wight PO30 3AR (36 components)
• (Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S23G01 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
• Cowes 2 - OCGT, fuel is distillate MSID: 4548
• The CMU component JENBA3 is a gas fired CHP engine rated at 1.845MW (1.942MW design output but derated at 95% due to age).
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Lynchford Lane, Farnborough, GU14 6LW (1 component)

10 gas reciprocating engines used for power generation, with associated infrastructure.

Inactive • 2023-24 (T-4)
Land West of Yelland Quay, West Yelland, Yelland, Barnstaple, EX31 3HB (2 components)
• 10 x 2MW gas reciprocating engines used for power generation, with associated infrastructure.
• Diesel and/or gas reciprocating engines.
Inactive • 2022-23 (T-4), 2020-21 (T-4)
Land to north of SPEN Drumcross GSP, Byers Brae, Bathgate EH54 8TB. See map. (12 components)
• Killingholme Module 2 converted to open cycle operation
• Load reduction
• The facility consists of a lithium Ion battery storage system capable of importing, storing and exporting electricity. It connects to SPEN?s 33kV distribution network at 33kV
Inactive • 2022-23 (T-4), 2022-23 (T-3) ...
LAND ON THE NORTH SIDE OF GALLEY HILL ROAD NORTHFLEET GRAVESEND DA11 9SW (9 components)
• CMU consisting of multiple reciprocating engines and alternators
• Existing OCGT
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Inactive • 2023-24 (T-4), 2023-24 (T-1) ...
9.63 MW
Land off Well Street, Paisley, PA1 2QH (2 components)

4 gas reciprocating engines used for power generation, with associated infrastructure.

Inactive • 2023-24 (T-4), 2022-23 (T-3)
Land off Bicester Road Bicester Oxfordshire OX26 6EP (2 components)
• Gas fuelled generation plant
• Office site with behind the meter bio-diesel generation - offsetting site load and exporting surplus
Inactive • 2022-23 (T-4), 2022-23 (T-3)
Land off B1165 Spalding PE12 8PT (1 component)

This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-9G under the BSC.

Inactive • 2022-23 (T-4)
Land at Strasbourg St, Westwood Industrial Estate, Margate, Kent, CT9 4JF (13 components)
• 20.7MW power plant comprising reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 20MW power plant comprising reciprocating engines. The power plant will be connected to the local distribution network and local gas network.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-12G under the BSC.
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
LAND AT FENTON LANE LITTLE FENTON SHERBURN IN ELMET LS25 6HA (5 components)
• Load Response - Automated Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• NEW BUILD GAS GENERATION STATION
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Land at Fawley , Northern Access Road, Southampton, SO45 1BD  (7 components)
• CMU Component is 500kVA reciprocating diesel engine.
• Gas Turbine CHP GT001B
• Taylor's Lane OCGT GT Unit 3 Unit fuelled by Gas Oil as specified in BS 2869 Class A2
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Land at Crown Farm, King John Bank, Walpole St. Andrew, Wisbech, Norfolk, PE13 5PR (16 components)
• Gas fuelled generation plant
• Industrial Steelmaking / Manufacturing Site. The DSR capacity (MW) is the proven DSR capacity. The DSR Test Certificate applies to TS16_1, cloned to TS17_1 and then cloned to TS18_1
• One of three CHP units at Energy Center, Ashton Street, Liverpool, L69 3GBNY 25354 48843
Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
Land adjacent to Brynfyrd, Botley Road, Romsey, SO52 9DP (3 components)

10 x 2MW gas powered generator units to be installed on designated land within a manufacturing compound at the Botley Farm.

Inactive • 2021-22 (T-1)
Loading map...
Showing 25 locations