Open Cycle Gas Turbine (OCGT)

5 unique locations (271 components)

Burghfield Mini Power Plant, Cottage Lane, Pingewood, Reading, RG30 3UW (29 components)
• 1 x OCGT
• Commercial printers
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2028-29 (T-4), 2027-28 (T-4) ...
577.46 MW
Cowes Power Station Kingston Road East Cowes Isle of Wight PO32 6JS (37 components)
• Cowes 1 - OCGT, fuel is distillate MSID: 4548
• Cowes 2 - OCGT, fuel is distillate MSID: 4548
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
498.22 MW
EDF Energy (Thermal Generation) Limited, West Burton A Power Station, West Burton, Retford, Nottinghamshire, DN22 9BL (142 components)
• Genset 2.
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUGT-4 = 100% (T_WBUGT-4)
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-4 = 100% (T_WBUPS-4) + 25% (E_WBUPS-STX)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
2472.54 MW
Eggborough Power Station, Goole, East Yorkshire, DN14 0BS (56 components)
• BM unit T_DINO-6 at Dinorwig Power Station (Pumped Storage)
• Battery Energy Storage System built on land at the former Eggborough Power Station (Unit 7)
• New build Open Cycle Gas Turbine unit 5 at Eggborough Power Station
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4657.99 MW
Peterborough Power Station, Storeys Bar Road, Peterborough, PE1 5NT (7 components)
• 20 x 1mw Battery Storage units to be installed on designated land at Greenfield Road - Connection offer is for 40mw which is split between CMUs - further detail in covering letter
• Existing OCGT plant.
• Hospital
Active • 2028-29 (T-4), 2027-28 (T-4) ...
918.41 MW