18 unique locations (611 components)

Winnington CHP Winnington Lane Winnington Northwich Cheshire CW8 4GX (47 components)
β€’ Continuously operating, maximum output GE gas turbine driving a 47.020MVA Alstom generator at 0.85 power factor.
β€’ Continuously operating, maximum output GE gas turbine driving a 47.020MWA Alstom generator at 0.85 power factor.
β€’ Continuously operating, variable output Man Diesel Turbo single pass-out back pressure turbine driving a 19.300 MVA TD Power Systems generator at 0.85 power factor.
Active β€’ 2028-29 (T-4), 2026-27 (T-4) ...
232.80 MW
Villa Nursery, Reeves Lane, Roydon, Harlow, Essex, CM19 5LE (25 components)
β€’ A generating station consisting on multiple reciprocating engines and alternators located on a single site
β€’ Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
β€’ Standby generation
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
8.06 MW
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
β€’ Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
β€’ Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
β€’ Hydro power turbine generator Unit 4 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
Saltend Lane, HULL, HU12 8PP (33 components)
β€’ Load reduction
β€’ Load reduction on site
β€’ On-site CHP - existing generating unit Maesgwyn Farm, Chirk, Wrexham, LL14 5NT SJ 284 383
Active β€’ 2028-29 (T-4), 2025-26 (T-4) ...
14.86 MW
Rannoch Power Station, Rannoch, Perthshire, PH17 2QP (49 components)
β€’ 1 x hydro turbine & synchronous generator
β€’ 3 x 2MW Gas fuelled generator units to be installed on designated land within a compound at Belvedere Nurseries
β€’ one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
207.87 MW
Plot 6 Barrow Man Road, Birchington CT7 0AX (19 components)
β€’ CHP engine in a horticultural environment, natural gas, no aux load
β€’ New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
β€’ The CMU component at the Feeder Road Battery Storage Facility will be an energy storage system comprised of batteries and will have import and export capacity of 20.000MW each.
Active β€’ 2028-29 (T-4), 2024-25 (T-4) ...
14.72 MW
MytheΒ Road. Tewkesbury. Gloucester. GL20 6AA (18 components)
β€’ Load reduction on site supported by non-exporting standby generation.
β€’ The CMU component at Catsbrain Farm is an energy storage system comprised of Lithium-ion batteries. The system will have a 20 MW export capacity and an import capacity of 20 MW.
β€’ West Burton A Power Station Combined CMU WAC-21 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-3 = 100% (T_WBUPS-3) + 25% (E_WBUPS-STX)
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
7.15 MW
Mersey Wharf Business Park, Dock Road South, Bromborough Pool, Wirral, Merseyside, CH62 4SU (20 components)
β€’ 16 MW power plant comprising gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
β€’ 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
β€’ Ratcliffe Unit 3 coal-fired unit
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
61.51 MW
Kings Yard Energy Centre, Carpenters Lane, Stratford, London E15 2DU (35 components)
β€’ A Battery Energy Storage System.
β€’ Combined Heat and Power Plant Olympic Park London
β€’ Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the combined peak of all the component units to determine the capacity of LDEC as a single CMU hence the connected capacity above being consistent with the three peaks of the combined units.
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
14.68 MW
Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom (13 components)
β€’ BM Unit T_FFES-3 at Ffestiniog Power Station (Pumped Storage)
β€’ Unit 5 is a Cogenation unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG-19, EMD-19 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power and steam generation units on site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02). Gross 3 HH av. peak generation from Unit 5 on separate days = 141.040 MW At these three HH times, aux load on Unit 5 = 2.597 MW Net generation from Unit 5 = 138.443 MW
β€’ Unit 5 is a Cogeneration unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG244 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power generation units on the site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment, the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02).
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
382.93 MW
EDF Energy (Thermal Generation) Limited, West Burton A Power Station, West Burton, Retford, Nottinghamshire, DN22 9BL (142 components)
β€’ Genset 2.
β€’ West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUGT-4 = 100% (T_WBUGT-4)
β€’ West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-4 = 100% (T_WBUPS-4) + 25% (E_WBUPS-STX)
Active β€’ 2027-28 (T-4), 2026-27 (T-4) ...
2472.54 MW
Crown Point Glasshouse, Kirby Road, Norwich, NR14 7DU (2 components)
β€’ 3No 1.2MW gas CHP providing power, heat and CO2 in a horticultural environment
β€’ Gas fired reciprocating engines.
Active β€’ 2024-25 (T-4), 2021-22 (T-4)
Chase Hill Road Killingholme North Lincolnshire DN40 3LU (35 components)
β€’ A 7.5MW Tesla Battery Energy Storage System
β€’ Killingholme Module 1 converted to open cycle operation
β€’ Killingholme Module 2 converted to open cycle operation
Active β€’ 2028-29 (T-4), 2026-27 (T-4) ...
2098.53 MW
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (57 components)
β€’ CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
β€’ The CMU component is a combined cycle gas turbine
β€’ one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active β€’ 2028-29 (T-4), 2027-28 (T-4) ...
3488.59 MW
Barnsley Facilities Services Limited Estates & Facilities Department Gawber Road Barnsley S75 2EP (14 components)
β€’ 1 MW CHP generation
β€’ 30MW/30MWh one hour battery storage asset located near BURWB1 asset
β€’ Siemens SGT200 based CHP
Active β€’ 2026-27 (T-4), 2024-25 (T-4) ...
5.34 MW
Asda Witham Highfields Road, Benfield Way Lakes Road Braintree CM7 3YS (10 components)
β€’ CHP unit
β€’ Load reduction.
β€’ New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active β€’ 2026-27 (T-4), 2025-26 (T-4) ...
5.71 MW
ASDA Washington ADC, Pattinson Ind Est District 15, NE38 8QA (12 components)
β€’ Existing OCGT
β€’ Load curtailment from refridgeration
β€’ Load reduction from refrigeration
Active β€’ 2028-29 (T-4), 2024-25 (T-4) ...
20.36 MW
1A Elms Farm Industrial Estate Edison Road Bedford Bedfordshire MK41 0HU (15 components)
β€’ 2 x 2MW Gas fuelled generator units to be installed on designated land within a compound at Waterswallows Road
β€’ A completed power plant, with associated civil works, switchgear and electrical connection.
β€’ Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW.
Active β€’ 2026-27 (T-4), 2025-26 (T-4) ...
7.90 MW
Loading map...
Showing 18 locations