Winnington CHP Winnington Lane Winnington Northwich Cheshire CW8 4GX (47 components)
• Continuously operating, maximum output GE gas turbine driving a 47.020MVA Alstom generator at 0.85 power factor.
• Continuously operating, maximum output GE gas turbine driving a 47.020MWA Alstom generator at 0.85 power factor.
• Continuously operating, variable output Man Diesel Turbo single pass-out back pressure turbine driving a 19.300 MVA TD Power Systems generator at 0.85 power factor.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
232.80 MW
Windsor Battery East, Millstream East, Maidenhead Road, Windsor, Berkshire, SL4 5GD. (10 components)
• Battery Storage
• Gas reciprocating engines
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
Active • 2026-27 (T-4), 2025-26 (T-4) ...
0.09 MW
Tummel Power Station, Pitlochry, Perthshire, PH16 5SB (41 components)
• 1 x hydro turbine & synchronous generator
• Battery Energy Storage system operating alongside solar farm
• Solar Farm consisting of solar PV modules and inverters
Active • 2028-29 (T-4), 2027-28 (T-4) ...
104.16 MW
The Abbatoir, Brandon Rd, Watton, Thetford, IP25 6LW, United Kingdom (22 components)
• Grid-scale energy storage system based on Lithium Ion, capable of exporting 8MW for a 1 hour duration installed on designated land within a compound at Belvedere Nurseries
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• The component consists of gas CHP (2679kW and 2004kW) servicing the electricity and heat requirements for Aldergrove Nursery, one of the horticultural sites which trades at Flavourfresh Salads. All generation unit capacities are nominal and allow for site-specific variations.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4.34 MW
Staythorpe Power Station Staythorpe Newark Nottinghamshire NG23 5PS (60 components)
• Staythorpe 1 - CCGT MSID: 7210
• Staythorpe 2 - CCGT MSID: 7210
• Staythorpe 4 - CCGT MSID: 7210
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6050.24 MW
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 4 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
Saltend Lane, HULL, HU12 8PP (33 components)
• Load reduction
• Load reduction on site
• On-site CHP - existing generating unit Maesgwyn Farm, Chirk, Wrexham, LL14 5NT SJ 284 383
Active • 2028-29 (T-4), 2025-26 (T-4) ...
14.86 MW
Rannoch Power Station, Rannoch, Perthshire, PH17 2QP (49 components)
• 1 x hydro turbine & synchronous generator
• 3 x 2MW Gas fuelled generator units to be installed on designated land within a compound at Belvedere Nurseries
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
207.87 MW
New Galloway, Castle Douglas, Kirkcudbrightshire, DG7 3SF, Scotland (43 components)
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 2, part of the Galloway hydroelectric scheme The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
78.70 MW
Marks & Spencer - Stockley Park, 3 Longwalk Road, Stockley Park, Uxbridge, UB11 1AW (10 components)
• Glenlee hydro power station - Unit 2, part of the Galloway hydroelectric scheme The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Load reduction
• Office site with behind the meter bio-diesel generation - offsetting site load and exporting surplus
Active • 2025-26 (T-4), 2023-24 (T-4) ...
0.77 MW
Inverawe Power Station, Inverawe, by Taynuilt, Argyll, PA35 1HU (24 components)
• 1 x hydro turbine & synchronous generator
• 1x hydro turbine & synchronous generator
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2028-29 (T-4), 2027-28 (T-4) ...
91.46 MW
Greatmoor EfW, Greatmoor Road, Woodham, Aylesbury, Buckinghamshire, HP18 0QE (16 components)
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
• Genset 2.
• This CMU identifier is the replacement for BUCK01, BUCK02, FCCB01, due to the change in Connection Capacity as per rule 3.5.2 and change from "New build CMU" to "Existing CMU" status FCC Buckinghamshire Ltd. 300kT Energy from Waste Plant with c. 25MW net output. Auxiliary load is not included in the connection capacity i.e the export is net.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
94.17 MW
Fiddler's Ferry Power Station, Widnes Road, Cuerdley, Warrington, WA5 2UT (166 components)
• GT3
• Genset 1.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2027-28 (T-4), 2025-26 (T-4) ...
13899.76 MW
Errochty Power Station, Tummel Bridge, Pitlochry, PH16 5NT (27 components)
• Generating Unit 1
• Generating Unit 2
• Generating Unit 3
Active • 2028-29 (T-4), 2027-28 (T-4) ...
267.57 MW
EDF Energy, Torness power station, Torness, Dunbar, East Lothian, EH42 1QU (34 components)
• Torness Power Station CMU 1: [TN1-23] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 1: [TN1-24] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 2: [TN2-24] T_TORN-2 + (50% x T_TORN-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3068.68 MW
EDF Energy (Thermal Generation) Limited, West Burton A Power Station, West Burton, Retford, Nottinghamshire, DN22 9BL (142 components)
• Genset 2.
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUGT-4 = 100% (T_WBUGT-4)
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-4 = 100% (T_WBUPS-4) + 25% (E_WBUPS-STX)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
2472.54 MW
EDF Energy (Thermal Generation) Limited, Cottam Power Station, Outgang Lane, Cottam, Retford, DN22 0NP (46 components)
• 2MW - 2.3MWh Battery Energy Storage System
• CMU INO200 represents demand assets on the Inovyn ChlorVinyls Ltd site in Runcorn, Cheshire. The asset uses electricity for Chemical manufacture. Site load can easily be altered to suit demand or reduction.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1528.52 MW
Clunie Power Station, Pitlochry, PH16 5NF (11 components)
• Combination of load curtailment and standby generation
• Hydro Generating Gensets 1, 2 & 3 - Clunie
• ROCable hydro units within the BMU are not included in the CMU.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
12.78 MW
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (57 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• The CMU component is a combined cycle gas turbine
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3488.59 MW
Bury St Edmunds Sugar Factory British Sugar plc Hollow Road Bury St Edmunds IP32 7BB (12 components)
• 1 x hydro turbine & synchronous generator
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
• The CMU is a gas fired CCGT CHP
Active • 2028-29 (T-4), 2026-27 (T-4) ...
275.68 MW
Asda South Shields, Coronation Street NE33 1AZ (8 components)
• Generating Unit 2
• Load curtailment from refridgeration
• Load drop
Active • 2028-29 (T-4), 2025-26 (T-4) ...
23.52 MW
Asda Sefton Park, 126 Smithdown Road , Liverpool, L15 3JR (11 components)
• Genset 3
• Load curtailment
Active • 2028-29 (T-4), 2025-26 (T-4) ...
49.71 MW
Asda Norwich, Drayton High Road, Hellesdon, NR6 5DT (12 components)
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Load curtailment from refridgeration
• Load reduction from refrigeration
Active • 2028-29 (T-4), 2025-26 (T-4) ...
20.36 MW
Asda Dyce, River View Drive , Aberdeen, AB21 7NG (11 components)
• 1 x hydro turbine & synchronous generator
• Load curtailment
Active • 2028-29 (T-4), 2025-26 (T-4) ...
45.43 MW
Asda Dundee Milton, Milton Of Craigie Longtown Road, Dundee, DD4 7RX (11 components)
• Generating unit 3.
• Load curtailment
Active • 2028-29 (T-4), 2025-26 (T-4) ...
31.73 MW
Loading map...
Showing 25 locations