5 unique locations (154 components)

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS (19 components)
• (Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S24S11 is a Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.
• (Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). Unit is a OCGT and Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.
• Keadby GT3
Active • 2028-29 (T-4), 2026-27 (T-4) ...
132.13 MW
Keadby Power Station Trentside, Keadby, Scunthorpe, DN17 3EF (59 components)
• Keadby 1 CCGT
• Keadby GT3
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2028-29 (T-4), 2027-28 (T-4) ...
5902.68 MW
Furniss & White, 17 Abbey Way, North Anston Trading Estate, North Anston, Sheffield, S25 4JL (24 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• The facility consists of a lithium Ion battery storage system capable of importing, storing and exporting electricity. It connects to SPEN?s 33kV distribution network at 33kV.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
20.91 MW
British Steel Limited, Administration Building, Brigg Road, Scunthorpe, North Lincolnshire, DN16 1XA (46 components)
• Hamms Hall - Existing Site CHP
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• existing CHP on site
Active • 2028-29 (T-4), 2027-28 (T-4) ...
179.28 MW
Asda Isle of Dogs, 3 Nutmeg Ln, London E14 2AX (6 components)
• GT3
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Load reduction on site supported by non-exporting standby generation.
Active • 2026-27 (T-4), 2024-25 (T-4) ...