Home Technologies Companies Locations Map Explorer FAQ ChatGPTChatGPT Buy Me A Coffee Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

DSR (Demand Side Response)

7 unique locations (88 components)

Unit 28,29,30, Peel Mills Industrial Estate, Chamberhall Street, Bury, BL9 0LU (19 components)
• 16MW power plant comprising of reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• EV charging at residential premises
• Generating Unit 2
Active • 2028-29 (T-4), 2027-28 (T-4) ...
52.05 MW
Millerhill Recycling & Energy Recovery Centre Whitehill Road DALKEITH EH22 1SX (12 components)
• FCC (E+M) Limited, 170kT Energy from Waste plant at Newcraighall with estimated 14 MW Generation Capacity. Auxilliary load is not included in connection capacity .i.e the export is net.
• Generating Unit 2
• New CMU ID due to updated Grid Connection Agreement FCC (E+M) Limited, 170kT Energy from Waste plant at Newcraighall with estimated 14 MW Generation Capacity. Auxilliary load is not included in connection capacity .i.e the export is net.
Active • 2028-29 (T-4), 2024-25 (T-4) ...
46.94 MW
Land Adjacent to Stobarts Logistics Off Branthwaite Road Lillyhall Workington Cumbria CA14 4ED (16 components)
• Gas reciprocating engines
• Generating Unit 2
• The East West Interconnector (EWIC) is a 400kV HVDC link between Connah's Quay in Wales and Woodland in Ireland.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
22.75 MW
Kingsnorth. Hoo. St Werburgh. Rochester. Kent. ME3 9TX (Next to Damhead Creek Power Station CMU SP17DC) (6 components)
• 1 x hydro turbine & synchronous generator
• New build Open Cycle Gas Turbine plant
• bus depot
Active • 2026-27 (T-4), 2024-25 (T-4) ...
1557.00 MW
Foyers Power Station, Kelvin Way, Gorthleck, Foyers, Inverness-shire, IV2 6YB (17 components)
• Component has yet to be procured.
• Gas peaking reciprocating engines
• Generating Unit 1
Inactive • 2022-23 (T-4), 2021-22 (T-4) ...
204.51 MW
Fasnakyle Power Station, Cannich, Beauly, IV4 7NB (10 components)
• Generating Unit 1
• Generating Unit 2
• Generating unit 3.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
104.92 MW
Asda South Shields, Coronation Street NE33 1AZ (8 components)
• Generating Unit 2
• Load curtailment from refridgeration
• Load drop
Active • 2028-29 (T-4), 2025-26 (T-4) ...
23.52 MW
Loading map...
Showing 7 locations