5 unique locations (104 components)

Wissington Sugar Factory British Sugar plc College Road Wissington King's Lynn PE33 9QG (33 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Existing CCGT
• The CMU is a gas fired CCGT CHP
Active • 2028-29 (T-4), 2027-28 (T-4) ...
207.86 MW
Site of the former Teesside Power Station Greystone Road Grangetown Middlesbrough TS6 8JF (2 components)
• N/A
• Tees CCPP is a 542.6MW CCGT unit to be installed on designated land within the (former ICI) Wilton Site this will be connected to Greystones 275kV 'A' Substation and Greystones 275kV 'B' Substation.
Inactive • 2023-24 (T-4)
488.34 MW
Site of the former Teesside Power Station Greystone Road Grangetown Middlesbrough TS6 8JF (1 component)

Tees CCPP is a 542.6MW CCGT unit to be installed on designated land within the (former ICI) Wilton Site this will be connected to Greystones 275kV 'A' Substation and Greystones …

Inactive • 2023-24 (T-4)
Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom (12 components)
• CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S26G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW.
• Didcot B6 - CCGT MSID: 4055
Active • 2028-29 (T-4), 2027-28 (T-4) ...
762.63 MW
Eggborough Power Station, Goole, East Yorkshire, DN14 0BS (56 components)
• BM unit T_DINO-6 at Dinorwig Power Station (Pumped Storage)
• Battery Energy Storage System built on land at the former Eggborough Power Station (Unit 7)
• New build Open Cycle Gas Turbine unit 5 at Eggborough Power Station
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4657.99 MW