4 unique locations (135 components)

Academy CHP, Lodge Avenue, Academy Way, Dagenham, London, RM8 2JA (14 components)
• 20 x 1mw gas generator units to be installed on designated land at Stratford Road - Connection offer is for 41.24mw which is split between CMUs - further detail in covering letter
• A as engine CHP site providing hot water to a local district heating network
• A gas engine CHP site providing hot water to a local district heating network
Active • 2028-29 (T-4), 2026-27 (T-4) ...
1.20 MW
Cargill PLC, Trafford Park, Manchester, M17 1PA (69 components)
• Siemens SGT200 based CHP
• Solar T70 Based CHP System
• Solar T70 based CHP system
Active • 2028-29 (T-4), 2025-26 (T-4) ...
93.80 MW
Land At Junction With Hunsley Street and Carlisle Road, Sheffield, S4 8DQ (25 components)
• 1,000MW electricity interconnector between GB and Belgian transmission systems. The Nemo Link interconnector will consist of subsea and underground cables connected to a converter station in each country, which will allow electricity to flow in either direction between the two countries. Nemo Link® will build the converter station on an 8 hectare site, formerly occupied by the Richborough Power Station, which now forms part of the Richborough Energy Park proposals. A similar converter station will be built in the industry zone Herdersbrug in Bruges.
• Battery energy storage unit
• Two gas CHP in a horticultural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
21.52 MW
Lansdale Nursery, Jacksmere Lane, Scarisbrick, Ormskirk, Lancs L40 9RT (27 components)
• New build onshore wind farm project. 13 no. wind turbine generator wind farm with an installed capacity of 62.4MW located in South Lanarkshire, Southern Scotland
• One asset 2.0MW CHP engine in a horticultural environment with no auxiliary load.
• One of three CHP in a horticultural environment.
Active • 2025-26 (T-4), 2025-26 (T-1) ...
1.65 MW
Loading map...