Home Technologies Companies Locations Map Explorer FAQ ChatGPTChatGPT Buy Me A Coffee Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

Combined Heat and Power (CHP)

3 unique locations (218 components)

Europa Energy Centre, Hills Court Road, Ash, Kent, CT3 2AP (30 components)
• The CMU Component will have a connection capacity of 15MW. Gas-fired reciprocating engine will be the technology used.
• The CMU component BREH01 consists of one CHP engine supplying heat, CO2 and power to the on site Nursery.
• The CMU component BREH02 consists of one CHP engine supplying heat, CO2 and power to the on-site Nursery.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
95.49 MW
EDF Energy (Thermal Generation) Limited, West Burton A Power Station, West Burton, Retford, Nottinghamshire, DN22 9BL (142 components)
• Genset 2.
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUGT-4 = 100% (T_WBUGT-4)
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-4 = 100% (T_WBUPS-4) + 25% (E_WBUPS-STX)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
2472.54 MW
EDF Energy (Thermal Generation) Limited, Cottam Power Station, Outgang Lane, Cottam, Retford, DN22 0NP (46 components)
• 2MW - 2.3MWh Battery Energy Storage System
• CMU INO200 represents demand assets on the Inovyn ChlorVinyls Ltd site in Runcorn, Cheshire. The asset uses electricity for Chemical manufacture. Site load can easily be altered to suit demand or reduction.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1528.52 MW
Loading map...
Showing 3 locations