Combined Heat and Power (CHP)

10 unique locations (646 components)

APS Growers Ltd / Branfield Nursery 111 Stockbridge Road Elloughton HU15 1HW (15 components)
• A New Build 2.5MW Generation Battery Site
• One Jenbacher CHP engine with a generation capacity of 3.36 MW
• Onsite load reduction and back up generation behind the meter on multiple sites
Active • 2028-29 (T-4), 2027-28 (T-4) ...
12.31 MW
Aston University, Aston Triangle, Birmingham, West Midlands, B4 7ET (57 components)
• 1MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• 2MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• Containerised high speed gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 9MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
13.92 MW
Drax Power Station, Selby, North Yorkshire, YO8 8PH (67 components)
• A coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-5.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-12G under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-9G.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1001.79 MW
EDF Energy, Hartlepool power station, Tees Road, Hartlepool, TS25 2BZ (57 components)
• Hartlepool Power Station CMU 2: [HR2-23] T_HRTL-2
• Hartlepool Power Station CMU 2: [HR2-24] T_HRTL-2
• Hartlepool Power Station CMU 1: [HR1-24] T_HRTL-1
Active • 2028-29 (T-4), 2027-28 (T-4) ...
5859.76 MW
EDF Energy (Thermal Generation) Limited, West Burton A Power Station, West Burton, Retford, Nottinghamshire, DN22 9BL (142 components)
• Genset 2.
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUGT-4 = 100% (T_WBUGT-4)
• West Burton A Power Station Combined CMU WAC-22 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-1 = 100% (T_WBUPS-1) + 25% (E_WBUPS-STX)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
2472.54 MW
Europa Energy Centre, Hills Court Road, Ash, Kent, CT3 2AP (30 components)
• The CMU Component will have a connection capacity of 15MW. Gas-fired reciprocating engine will be the technology used.
• The CMU component BREH01 consists of one CHP engine supplying heat, CO2 and power to the on site Nursery.
• The CMU component BREH02 consists of one CHP engine supplying heat, CO2 and power to the on-site Nursery.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
95.49 MW
Fiddler's Ferry Power Station, Widnes Road, Cuerdley, Warrington, WA5 2UT (166 components)
• GT3
• Genset 1.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2027-28 (T-4), 2025-26 (T-4) ...
13899.76 MW
Lochay Power Station, Killin, Stirling, FK21 8UA (23 components)
• Genset 1.
• Genset 2.
• Genset 2. ROCable hydro units within the BMU are not included in the CMU.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
83.08 MW
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 5 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
Wood End, Stocks Lane, Over Peover, Knutsford WA16 9EZ (24 components)
• 2MW gas CHP engine in a horticultural environment
• One 1.354 MW gas CHP engine in a horticultural environment
• One 1.5 MW gas CHP engine in a horticultural environment
Active • 2028-29 (T-4), 2025-26 (T-4) ...
9.85 MW
Loading map...