Combined Cycle Gas Turbine (CCGT)

99 unique locations (1355 components) - Page 2 of 4

Active MW: 100429.76 MW
Inactive MW: 6087.60 MW
Redditch Generation Station, Windsor Road, Redditch, B97 6HE (5 components)
• Gas reciprocating engines as the generating unit. (2)
• Open cycle gas turbine as the generating unit.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
68.21 MW
Redditch Generation Station Windsor Road Redditch B97 6HE (3 components)

Gas turbine generator (3)

OCGT Open Cycle Gas Turbine (OCGT) ALKANE ENERGY UK LIMITED Existing Generating CMU Redditch Redditch B97
Active • 2025-26 (T-4), 2021-22 (T-4) ...
Redditch Generation Station Windsor Road Redditch B97 6HE (3 components)

Gas turbine generator (3)

Open Cycle Gas Turbine (OCGT) ALKANE ENERGY UK LIMITED Existing Generating CMU Redditch Redditch B97
Active • 2024-25 (T-1), 2023-24 (T-1) ...
46.34 MW
Ratcliffe-on-Soar Nottingham NG11 0EE (44 components)
• Ratcliffe U2 OCGT fuelled on Diesel as defined by BS EN590 (2)
• Ratcliffe U4 OCGT fuelled on Diesel as specified by BS EN590
Active • 2028-29 (T-4), 2027-28 (T-4) ...
30.19 MW
Ratcliffe-on-Soar Nottingham NG11 0EE (16 components)
• Ratcliffe U2 OCGT fuelled on Diesel as defined by BS EN590 (2)
• Ratcliffe U4 OCGT fuelled on Diesel as specified by BS EN590
Coal Open Cycle Gas Turbine (OCGT) UNIPER UK LIMITED Existing Generating CMU Ratcliffe GT2 Ratcliffe GT2 +13 more NG11
Active • 2025-26 (T-1), 2023-24 (T-1) ...
475.11 MW
Progress Power Station, Eye Airfield, Diss, Suffolk, IP23 7HE (5 components)
• A new 299MW Open Cycle Gas Turbine (OCGT) power peaking plant (2)
• A new Open Cycle Gas Turbine (OCGT) power peaking plant
Open Cycle Gas Turbine (OCGT) OCGT and Reciprocating Engines (Fuel Type - Gas) PROGRESS POWER LIMITED New Build Generating CMU Progress Power OCGT Progress Power OCGT +2 more IP23
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Power Station Road Isle of Grain Rochester ME3 0AR (50 components)
• Grain B CCGT Unit 6 Grain B power station provides heat to the Grain LNG regasification facility.
• Grain B CCGT Unit 7 Grain B power station provides heat to the Grain LNG regasification facility.
• Grain B CCGT Unit 8. Grain B power station provides heat to the Grain LNG regasification facility.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4000.25 MW
Peterhead Power Station, Peterhead, Aberdeenshire, AB42 3BZ (15 components)

Peterhead CCGT (3)

Combined Cycle Gas Turbine (CCGT) SSE THERMAL GENERATION (SCOTLAND) LIMITED Existing Generating CMU Peterhead Peterhead +12 more AB42
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3242.27 MW
Peterborough Power Station, Storeys Bar Road, Peterborough, PE1 5NT (4 components)

Existing OCGT plant. (3)

Open Cycle Gas Turbine (OCGT) RIVER NENE POWER LIMITED Existing Generating CMU Peterborough Power Peterborough Power +2 more PE1
Active • 2028-29 (T-4), 2027-28 (T-4) ...
690.18 MW
Pembroke Power Station Pembroke Dyfed SA71 5SS (50 components)
• Pembroke 11 - CCGT MSID: 7237
• Pembroke 21 - CCGT MSID: 7237
• Pembroke 31 - CCGT MSID: 7237
CCGT Combined Cycle Gas Turbine (CCGT) RWE GENERATION UK PLC Existing Generating CMU CMU_PEMB-11 CMU_PEMB-11 +43 more SA71
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6183.38 MW
Newton Aycliffe CO Durham DL5 6EA (9 components)

Existing Gas Engine (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
4.78 MW
Newton Aycliffe CO Durham DL5 6EA (6 components)

Existing Gas Engine (3)

Active • 2024-25 (T-1), 2023-24 (T-1) ...
3.22 MW
New Hall Farm School Lane Birchwood Warrington WA3 6LH (3 components)

New Gas fulled generation station (3)

Open Cycle Gas Turbine (OCGT) NEW HALL FARM ENERGY LIMITED New Build Generating CMU NHF111 Rejected WA3
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Mitchell Road, Phoenix Parkway, Corby, Northamptonshire, NN17 5QT (22 components)
• The CMU is a gas plant, capable of running in either OCGT or CCGT modes (2)
• The CMU is a Open Cycle Gas Turbine (OCGT)
Open Cycle Gas Turbine (OCGT) Combined Cycle Gas Turbine (CCGT) CORBY POWER LIMITED Existing Generating CMU New Build Generating CMU Corby_1 Corby_1 +12 more NN17
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2104.31 MW
Millbrook Power Station, Rookery South Pit, Green Lane, Stewartby, Bedfordshire MK43 9LX (3 components)
• A new 299MW Open Cycle Gas Turbine (OCGT) power peaking plant (2)
• A new Open Cycle Gas Turbine (OCGT) power peaking plant
Open Cycle Gas Turbine (OCGT) MILLBROOK POWER LIMITED New Build Generating CMU Millbrook Power OCGT Millbrook Power OCGT MK43
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Medway Power Station, Rochester, Medway, ME3 0AG (15 components)

Medway CCGT (3)

Combined Cycle Gas Turbine (CCGT) MEDWAY POWER LIMITED Existing Generating CMU Medway Medway +12 more ME3
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4026.04 MW
Meaford Energy Centre, Meaford Business Park, Meaford Road, Meaford, Staffordshire, ST15 8UZ (4 components)

Gas Fired Generating Station (3)

Open Cycle Gas Turbine (OCGT) OCGT and Reciprocating Engines (Fuel Type - Gas) Meaford Energy Limited New Build Generating CMU Meaford Generating Station Meaford Generating Station +2 more ST15
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Marsh Green Industrial Park Marsh Barton Trading Estate Exeter Devon EX2 8NY (6 components)

Existing OCGT. (3)

Reciprocating engines Open Cycle Gas Turbine (OCGT) WHITETOWER ENERGY LIMITED Existing Generating CMU Exeter Power Exeter Power +4 more EX2
Active • 2028-29 (T-4), 2027-28 (T-4) ...
128.10 MW
Marchwood Power, Marchwood Industrial Park, Oceanic Way, Marchwood, Southampton, SO40 4BD (10 components)

Marchwood CCGT (3)

Combined Cycle Gas Turbine (CCGT) SSE ENERGY SUPPLY LIMITED Existing Generating CMU Marchwood Marchwood +8 more SO40
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2519.70 MW
Lynchford Lane, Farnborough, GU14 6LW (4 components)

10 gas reciprocating engines used for power generation, with associated infrastructure. (3)

Open Cycle Gas Turbine (OCGT) Gas Generation Buckland Road Limited New Build Generating CMU Gas Generation Farnborough Gas Generation Farnborough +2 more Not Prequalified GU14
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Livesey Branch Rd, Feniscowles, Blackburn, Lancashire, BB2 5HX (10 components)
• Small Combined Cycle Gas Turbine plant with registered capacity 75MVA or 60MW at 0.8PF. (2)
• Small Combined Cycle Gas Turbine plant with contracted connection capacity 75MVA or 60MW at 0.8PF
Combined Cycle Gas Turbine (CCGT) VPI POWER LIMITED Existing Generating CMU Blackburn Mill Blackburn Mill +3 more BB2
Active • 2028-29 (T-4), 2027-28 (T-4) ...
221.95 MW
Little Barford Power Station Little Barford St Neots PE19 6YT (20 components)
• Little Barford 1 CCGT MSID: 4052 (2)
• Little Barford 1 OCGT . fuel type is distillate MSID: 4052
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2060.91 MW
Land off Well Street, Paisley, PA1 2QH (4 components)

4 gas reciprocating engines used for power generation, with associated infrastructure. (3)

Open Cycle Gas Turbine (OCGT) GAS GENERATION PROPERTY LIMITED New Build Generating CMU Gas Generation Paisley 1 Gas Generation Property +2 more PA1
Active • 2024-25 (T-4), 2023-24 (T-4) ...
land at Walton Common north of the National Grid Substation, Fort Road, Tilbury, RM18 8UL. (6 components)
• Gas reciprocating engines
• Thurrock Power Limited has secured a "blue chip" manufacturer as the EPC contractor to engineer, procure and construct a battery storage plant on at land at Walton Common north of the National Grid Substation, Fort Road, Tilbury, RM18 8UL.. Thurrock Power Limited will be constructed to be a brand new generating asset and is expected to have an equipment design life of 20 years. An experienced Operations & Maintenance contractor will be employed to ensure the plant is running effectively and efficiently to meet Capacity Market requirements. An Independent technical expert will be engaged to confirm the Plant will meet the Extended Years Criteria, Financial Commitment Milestone, and 6 monthly report for the Delivery Body as required under paragraph 8.3.6A of the Capacity Market Rules.
• Thurrock Power Limited has secured a "blue chip" manufacturer as the EPC contractor to engineer, procure and construct a gas power facility on at land at Walton Common north of the National Grid Substation, Fort Road, Tilbury, RM18 8UL.. Thurrock Power Limited will be constructed to be a brand new generating asset and is expected to have an equipment design life of 20 years. An experienced Operations & Maintenance contractor will be employed to ensure the plant is running effectively and efficiently to meet Capacity Market requirements. An Independent technical expert will be engaged to confirm the Plant will meet the Extended Years Criteria, Financial Commitment Milestone, and 6 monthly report for the Delivery Body as required under paragraph 8.3.6A of the Capacity Market Rules.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
817.08 MW
land at Hoon Hay Farm, Marston Lane, Hatton, Derbyshire, DE65 5EA (1 component)

gas powered generator to be installed on designated land within a manufacturing compound at the Hoon Hay Farm.

Active • 2024-25 (T-4)
Loading map...
Showing 25 locations