Combined Cycle Gas Turbine (CCGT)

5 unique locations (32 components)

Wheldale 1 Wheldale Generation Site Wheldale Road Castleford West Yorkshire WF10 2RR (6 components)
• Milling Motor Pelletizers, Fans etc
• New build Combined Cycle Gas Turbine unit 1 at Eggborough power station.
• load curtailment at site
Inactive • 2023-24 (T-4), 2021-22 (T-4) ...
Asda Ponders End, Iceland Foods 5 Solar Way Innova Park Brimsdown Enfield EN3 7XY (5 components)
• A CCGT station consisting of two Alstom GT26 gas turbines and a steam turbine and is based near Stanford-le-hope in Essex, England. Each turbine is individually metered with output being the total of all three turbines net of any auxillary load.
• Mix of load reduction and standby generation
Inactive • 2022-23 (T-3), 2021-22 (T-4) ...
Asda Dyce, Cairnton Road, Boyndie, Banffshire, AB45 2LR (8 components)
• Didcot B6 - CCGT MSID: 4055
• New Build gas fuelled generation station.
• This CMU component is a coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-6 under the BSC.
Active • 2026-27 (T-4), 2023-24 (T-4) ...
Asda Boston, Pudding Lane Spalding, Lincs, PE11 3TJ (7 components)
• 1 x Containerised High Speed Gas-fired reciprocating engines with an output of 2.5MW together with transformers, switchgear and associated control gear
• Load curtailment at site via standby generation
• West Burton B Power Station CMU 1 WB1-19= 100% T_WBURB-1
Inactive • 2022-23 (T-4), 2022-23 (T-3) ...
Asda Boston, Monument Road, Bicker, Lincolnshire PE20 3DJ (6 components)
• A new build 11MW battery storage system
• A new build gas fuelled generating station.
• Great Yarmouth 1 - CCGT MSID: 7111
Inactive • 2022-23 (T-3), 2021-22 (T-4) ...