Coal

36 unique locations (1179 components) - Page 2 of 2

EDF Energy (Thermal Generation) Limited, Cottam Power Station, Outgang Lane, Cottam, Retford, DN22 0NP (46 components)
• 2MW - 2.3MWh Battery Energy Storage System
• CMU INO200 represents demand assets on the Inovyn ChlorVinyls Ltd site in Runcorn, Cheshire. The asset uses electricity for Chemical manufacture. Site load can easily be altered to suit demand or reduction.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1528.52 MW
Drax Power Station, Selby, North Yorkshire, YO8 8PH (67 components)
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-10G under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-12G under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-9G.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1001.79 MW
Drax Power Station, Drax, Selby, YO8 8PH (23 components)
• On-site CHP - existing generating unit Pond Street London OS Grid Reference: TQ 272 854 NW3 2QG
• This CMU component is a coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-6 under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-10G under the BSC.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
341.88 MW
Chickerell Generation Site, Off Radipole Lane, Chickerell, Weymouth, DT3 4PA (17 components)
• 1 x OCGT
• A new build gas fuelled power generating unit comprising multiple reciprocating engines.
• Gas fuelled generation plant
Active • 2028-29 (T-4), 2027-28 (T-4) ...
265.86 MW
Asda Leek, Meerbrook, Leek, Staffordshire, ST13 8SN (8 components)
• 99.000MW Battery Energy Storage site
• Load reduction on site supported by non-exporting standby generation.
• West Burton A Power Station Combined CMU WAC-21 = 100% (T_WBUPS-1) + 100% (T_WBUPS-2) +100% (T_WBUPS-3) +100% (T_WBUPS-4) +100% (T_WBUGT-1) +100% (T_WBUGT-4)+ 100% (E_WBUPS-STX) Component T_WBUPS-4 = 100% (T_WBUPS-4) + 25% (E_WBUPS-STX)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
29.75 MW
Asda Dyce, Cairnton Road, Boyndie, Banffshire, AB45 2LR (8 components)
• Didcot B6 - CCGT MSID: 4055
• New Build gas fuelled generation station.
• This CMU component is a coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-6 under the BSC.
Active • 2026-27 (T-4), 2023-24 (T-4) ...
Aberthaw Power Station The Leys Aberthaw Barry Mid Glamorgan CF62 4ZW (9 components)
• Aberthaw 7 Coal fired unit
• Water pumping station comprising of electrical pumps that can be modulated or turned off.
Active • 2024-25 (T-4), 2022-23 (T-4) ...
411.53 MW
Aberthaw Power Station The Leys Aberthaw Barry Mid Glamorgan CF62 4ZW (8 components)

Aberthaw 7 Coal fired unit

Active • 2024-25 (T-4), 2023-24 (T-4) ...
54.62 MW
Aberthaw Power Station The Leys Aberthaw Barry Mid Glamorgan CF62 4ZW (90 components)
• E1000 CHP
• Existing CCGT
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2026-27 (T-4), 2024-25 (T-4) ...
2435.45 MW
501 Merlin Park, Burscough Industrial Estate, Ormskirk, L40 8JY (9 components)
• A coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-5.
• Gas and/or diesel reciprocating engines.
• New build power station comprised of multiple reciprocating engines.
Inactive • 2023-24 (T-4), 2021-22 (T-4) ...
323 Avebury Boulevard, MILTON KEYNES MK9 2GA (16 components)
• 1.200MW BESS
• A coal-fired boiler turbine unit at Drax Power Station with BMU identifier T_DRAXX-5.
• District heating implementation of two gas CHP engines with no auxilliary load
Active • 2026-27 (T-4), 2025-26 (T-4) ...
9.27 MW
Loading map...
Showing 11 locations