9 unique locations (47 components)

Abingdon Road, Luton, Bedfordshire, LU4 (1 component)

Domestic battery, charged by on site PV generation and grid supply. Charge and discharge managed via remotely controlled on-site control unit.

Active • 2025-26 (T-1)
8.23 MW (Est from CMU) (part of 8.23 MW aggregated CMU)
(Estimated)
Boxted Close, Luton, Bedfordshire, LU4 (1 component)

Domestic battery, charged by on site PV generation and grid supply. Charge and discharge managed via remotely controlled on-site control unit.

Active • 2025-26 (T-1)
8.23 MW (Est from CMU) (part of 8.23 MW aggregated CMU)
(Estimated)
Chapel Farm, Luton Road, Charlton, Luton, LU4 9UJ (8 components)
• 48 MW Battery Energy Storage facility
• 49.5 MW Battery Energy Storage facility
Active • 2025-26 (T-4), 2024-25 (T-4) ...
75.39 MW (Est from CMU)
(Estimated)
Dunstable Road, Luton, Bedfordshire, LU4 (1 component)

Domestic battery, charged by on site PV generation and grid supply. Charge and discharge managed via remotely controlled on-site control unit.

Active • 2025-26 (T-1)
8.23 MW (Est from CMU) (part of 8.23 MW aggregated CMU)
(Estimated)
East to Sundon NG Substation Chalton Luton LU4 9UQ (1 component)

30.000 MW standalone battery energy storage project

Active • 2026-27 (T-4)
3.54 MW
(Estimated)
Land south east of Sundon Substation Water End Lane Chalton, Luton LU4 9UB (3 components)

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.

Active • 2026-27 (T-4), 2025-26 (T-1)
32.75 MW (Est from CMU)
(Estimated)
LU4 (18 components)
• Domestic EV charger
• Domestic battery, charged by on site PV generation and grid supply. Charge and discharge managed via remotely controlled on-site control unit.
• Domestic demand turn down
Active • 2027-28 (T-4), 2025-26 (T-4) ...
86.46 MW (Est from CMU) (part of 86.46 MW aggregated CMU)
(Estimated)
Redmire Close, Luton , Beds, LU4 (1 component)

Domestic battery, charged by on site PV generation and grid supply. Charge and discharge managed via remotely controlled on-site control unit.

Active • 2025-26 (T-1)
8.23 MW (Est from CMU) (part of 8.23 MW aggregated CMU)
(Estimated)
XPO - Logistics Luton, Skimpot Road, Luton LU4 0JD (13 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.

Active • 2028-29 (T-4), 2024-25 (T-4) ...
17.61 MW (Est from CMU) (part of 17.61 MW aggregated CMU)
(Estimated)