Search Results for "PE11"

24 unique locations (99 components)

Asda Boston, Pudding Lane Spalding, Lincs, PE11 3TJ (6 components)
• Load curtailment via standby generation (2)
• Mixture of load reduction on flexible electricity consuming processes including refrigeration air-conditioning pumping and lighting and standby generation.
Inactive • 2022-23 (T-4), 2021-22 (T-4) ...
Bicker Road Donington Spalding PE11 4XR (1 component)

Energy storage system providing capacity market, dynamic FFR and other balancing services.

Inactive • 2021-22 (T-4)
Castle Sports Complex, Albion Street, PE11 2AJ (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Fowler Welch - Site 2, W Marsh Rd, Spalding PE11 2HR, UK (12 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Fowler Welch - Site 3, W Marsh Rd, Spalding PE11 2HR, UK (12 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Land And Buildings Whitehall, Gosberton PE11 4HQ (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Land off Bervor Close Pinchbeck Spalding PE11 3ZN (1 component)

Energy storage system providing capacity market, dynamic FFR and other balancing services.

Inactive • 2021-22 (T-4)
Land On The North West Side Of Roman Bank, Spalding, PE11 2HR (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Land On The South Side Of Holbeach Road, Spalding, PE11 2HX (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Parkside Crescent, Spalding, PE11 1QT (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Sir Halley Stewart Playing Field, Winfrey Avenue, Spalding, PE11 1DA (1 component)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network

Active • 2028-29 (T-4)
0.05 MW
Spalding STW, SPALDING STW, West Marsh Road, SPALDING Lincolnshire, PE11 2BB, (3 components)

The CMU Component reduces import demand by turning on back up generation. (2)

Inactive • 2020-21 (T-4), 2020-21 (T-1) ...
Viking Link, Bicker Fen Converter Station, North Ing Drove, Donnington, Spalding, Lincolnshire, PE11 4XY (3 components)

HVDC interconnector between GB and Danish transmission systems. Viking Link will involve the construction of two converter stations, sited in GB and Denmark. At the converter stations, alternating current electricity … (3)

Active • 2026-27 (T-4), 2025-26 (T-4) ...
Viking Link Ltd, Bicker Fen Converter Station, Northorpe Road, Donington SPALDING PE11 4XY (2 components)
• HVDC interconnector between GB and Danish transmission systems. Viking Link will involve the construction of two converter stations, sited in …
• Viking Link is a HVDC interconnector between GB and Danish transmission systems. Viking Link involved the construction of two converter …
Active • 2028-29 (T-4), 2027-28 (T-4)
Water Tower, Knight Street, Pinchbeck, Spalding, PE11 3XD (2 components)

CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network (2)

Active • 2027-28 (T-4), 2024-25 (T-1)
0.05 MW
West Marsh Road Spalding Lincolnshire PE11 2BB (3 components)
• A new combined cycle power station comprising gas turbine(s), heat recovery steam generator(s), steam turbine(s) and associated balance of plant. …
• A new combined cycle power station comprising the latest technology gas turbine(s), heat recovery steam generator(s), steam turbine(s) and associated …
• A new open cycle power station comprising gas turbine(s) and associated balance of plant. This will be constructed on brownfield …
Inactive • 2021-22 (T-4), 2020-21 (T-4)
West Marsh Road, Spalding, Lincolnshire, PE11 2BB (6 components)

A CCGT station consisting of two General Electric 9FA+e gas turbines with two VOGT-NEM heat recovery steam generators and one Hitachi steam turbine and is based near Spalding in Lincolnshire. … (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
1734.13 MW
West Marsh Road Spalding Lincolnshire PE11 3BB (14 components)

A new battery storage system comprising batteries, containers, inverters, control systems and associated balance of plant. This will be constructed on brownfield land in Spalding, Lincolnshire. Metering of output is … (3)

Active • 2025-26 (T-4), 2024-25 (T-4) ...
West Marsh Road, Spalding, Lincolnshire, PE11 3BB (6 components)

A CCGT station consisting of two General Electric 9FA+e gas turbines with two VOGT-NEM heat recovery steam generators and one Hitachi steam turbine and is based near Spalding in Lincolnshire. … (3)

Active • 2026-27 (T-4), 2025-26 (T-4) ...
867.73 MW
WEST PINCHBECK WTW, Parson Drove, Spalding, Lincolnshire, PE11 3QW (4 components)

Diesel Generator, Perkins (2)

Inactive • 2017-18 (T-1), 2016-17 (TR)
West Pinchbeck WTW, WEST PINCHBECK WTW, Parsons Drove, West Pinchbeck, SPALDING Lincolnshire, PE11 3QW, (3 components)

The CMU Component reduces import demand by turning on back up generation. (2)

Inactive • 2020-21 (T-4), 2020-21 (T-1) ...
W Marsh Rd, Spalding, PE11 2BB, United Kingdom (2 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. (2)

Active • 2024-25 (T-4), 2021-22 (T-1)
XPO - Spalding, W Marsh Rd, Spalding PE11 2HR, UK (12 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Loading map...
Showing 24 locations