Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Shingle Hall, Sawbridgeworth, CM21 6LX - A new build gas fuelled generating station.

Component ID: EDP003
Last updated: 24 Jul 2025 22:00 UTC
CMU ID:
Technology:
N/A
Description:
A new build gas fuelled generating station.
Auction:
2020-21 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 18.83
  • Connection Capacity (CMU Registry) 20 MW
  • Anticipated Capacity (CMU Registry) 18.83 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name Edge Power (Avro Business Park) Limited
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +441206203253

Field Value
_id 149313
Type T-4
rank 0.0706241
CMU ID EDP003
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
Component ID EDP003
Delivery Year 2020
De-Rated Capacity (empty)
OS Grid Reference TL 468 171
Location and Post Code Shingle Hall, Sawbridgeworth, CM21 6LX
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components A new build gas fuelled generating station.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 3988
Type T-4
CMU ID EDP003
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Avro Business Park
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2020
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 18.834
Name of Applicant Edge Power (Avro Business Park) Limited
Primary Fuel Type (empty)
Registered Holder Edge Power (Avro Business Park) Limited
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 20
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2020-EDP003-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 18.834
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2017-01-20
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 18.834
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+441206203253
Capacity Agreement has been Terminated Yes
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2020/2021, 2021/2022, 2022/2023, 2023/2024, 2024/2025, 2025/2026, 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement 2022-06-27
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2021-10-01