132 Manchester Road, Carrington, Manchester, M31 4AY - 250MW capacity system with 500MWh of batteries with all ancillary equipment to be installed on the Trafford Power Site

Component ID: TRAFBA
Last updated: 18 Jul 2025 15:35 UTC
CMU ID:
Description:
250MW capacity system with 500MWh of batteries with all ancillary equipment to be installed on the Trafford Power Site
Auction:
2025-26 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 99.33
  • Connection Capacity (CMU Registry) 250 MW
  • Anticipated Capacity (CMU Registry) 99.33 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name WAINSTONES ENERGY LIMITED
  • Parent Company (CMU Registry) Carlton Power Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401642714570

Field Value
_id 281905
Type T-4
rank 0.0706241
CMU ID TRAFBA
Auction Name 2025-26 (T-4) Four Year Ahead Capacity Auction
Component ID TRAFBA
Delivery Year 2025
De-Rated Capacity (empty)
OS Grid Reference SJ 726 929
Location and Post Code 132 Manchester Road, Carrington, Manchester, M31 4AY
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 2h)
Description of CMU Components 250MW capacity system with 500MWh of batteries with all ancillary equipment to be installed on the Trafford Power Site
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13220
Type T-4
CMU ID TRAFBA
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2025-26 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Trafford Power Battery Storage Unit 1
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Carlton Power Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 99.325
Name of Applicant WAINSTONES ENERGY LIMITED
Primary Fuel Type Storage - Battery
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 993250
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 250
Maximum Obligation Period 15
Capacity Agreement Awarded (empty)
Pre-Qualification Decision Not Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 99.325
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction (empty)
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401642714570
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)