Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Plot 3, Forge Way, Knypersley, Staffordshire, ST8 7DN - Knypersley Power will be a 7.012MW power plant comprising reciprocating engines. The power plant will be connected to the local distribution network and local gas network

Component ID: KPL001
Last updated: 22 Jul 2025 06:46 UTC
CMU ID:
Primary Fuel:
Gas
Description:
Knypersley Power will be a 7.012MW power plant comprising reciprocating engines. The power plant will be connected to the local distribution network and local gas network
Auction:
2028-29 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 6.56 MW
  • De-Rated Capacity (CMU Registry) 6.56
  • Connection Capacity (CMU Registry) 7.01 MW
  • Anticipated Capacity (CMU Registry) 6.56 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name Knypersley Power Limited
  • Parent Company (CMU Registry) Advica Holdings Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +447949789213

Field Value
_id 531007
Type T-4
rank 0.0706241
CMU ID KPL001
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
Component ID KPL001
Delivery Year 2028
De-Rated Capacity 6.556
OS Grid Reference SJ 880 557
Location and Post Code Plot 3, Forge Way, Knypersley, Staffordshire, ST8 7DN
Connection / DSR Capacity 7.012
Primary Fuel of Component Gas
Generating Technology Class Reciprocating engines
Description of CMU Components Knypersley Power will be a 7.012MW power plant comprising reciprocating engines. The power plant will be connected to the local distribution network and local gas network
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 15712
Type T-4
CMU ID KPL001
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name KPL001
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Advica Holdings Limited
DSR Test Method (empty)
Is FCM required Yes
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 6.556
Name of Applicant Knypersley Power Limited
Primary Fuel Type Gas
Registered Holder Knypersley Power Limited
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 65560
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 7.012
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2028-KPL001-001
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 6.556
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 6.556
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+447949789213
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone 2026-07-21
Delivery Years for which Agreement Valid 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042, 2042/2043
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2028-09-01
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2026-01-01
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2029-10-01