Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Uskmouth Power Station West Nash Road, Nash, Newport, Wales, NP18 2BZ - AW1 Energy Storage Limited (AW1) will develop a Battery Energy Storage System (BESS) at land adjacent to the substation and will initially develop a 120 MW / 240 MWh BESS at land adjacent to the substation, with energisation in October 2026 to achieve the Grid Connection Agreement with NGESO for connection to Uskmouth Substation at 132 kV. AW1 are developing then plans which include suitable Capacity Maintenance / Augmentation, and further are developing plans due to available space that the site system could be expanded in the future should the opportunity prevail.

Component ID: USKAW1
Last updated: 22 Jul 2025 01:31 UTC
CMU ID:
Primary Fuel:
Storage - Battery
Description:
AW1 Energy Storage Limited (AW1) will develop a Battery Energy Storage System (BESS) at land adjacent to the substation and will initially develop a 120 MW / 240 MWh BESS at land adjacent to the substation, with energisation in October 2026 to achieve the Grid Connection Agreement with NGESO for connection to Uskmouth Substation at 132 kV. AW1 are developing then plans which include suitable Capacity Maintenance / Augmentation, and further are developing plans due to available space that the site system could be expanded in the future should the opportunity prevail.
Auction:
2028-29 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 20.10 MW
  • De-Rated Capacity (CMU Registry) 20.10
  • Connection Capacity (CMU Registry) 96 MW
  • Anticipated Capacity (CMU Registry) 20.10 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name AW1 ENERGY STORAGE LIMITED
  • Parent Company (CMU Registry) AW1 Storage Holdings Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +447953134490

Field Value
_id 531066
Type T-4
rank 0.0706241
CMU ID USKAW1
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
Component ID USKAW1
Delivery Year 2028
De-Rated Capacity 20.102
OS Grid Reference ST 329 840
Location and Post Code Uskmouth Power Station West Nash Road, Nash, Newport, Wales, NP18 2BZ
Connection / DSR Capacity 96
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 2h)
Description of CMU Components AW1 Energy Storage Limited (AW1) will develop a Battery Energy Storage System (BESS) at land adjacent to the substation and will initially develop a 120 MW / 240 MWh BESS at land adjacent to the substation, with energisation in October 2026 to achieve the Grid Connection Agreement with NGESO for connection to Uskmouth Substation at 132 kV. AW1 are developing then plans which include suitable Capacity Maintenance / Augmentation, and further are developing plans due to available space that the site system could be expanded in the future should the opportunity prevail.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 16054
Type T-4
CMU ID USKAW1
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Afon Wysg 1
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company AW1 Storage Holdings Limited
DSR Test Method (empty)
Is FCM required Yes
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 20.102
Name of Applicant AW1 ENERGY STORAGE LIMITED
Primary Fuel Type Storage - Battery
Registered Holder AW1 ENERGY STORAGE LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 201020
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 96
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2028-USKAW1-001
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 20.102
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 20.102
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+447953134490
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone 2026-07-21
Delivery Years for which Agreement Valid 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042, 2042/2043
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2026-11-30
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2026-10-31
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2029-10-01