Search Map View Statistics Support Us Help Login Register
Linton, Highnam, Tewkesbury, Gloucestershire GL2 8AA
2 Components Storage (Duration 2h) STOR 136 LTD
Total Capacity: 38.98 MW
Components: 2
Technologies:
Storage (Duration 2h)
Unique CMUs: 2

Secondary Trading Contacts

Contact Information

Component Descriptions

Energy facility comprising of battery energy storage sets and ancillary equipment.

Used by 2 CMUs

CMU Identifiers

Components at this Location

Energy facility comprising of battery energy storage sets and ancillary equipment.
CMU: STOR36
Storage (Duration 2h) STOR 136 LTD Parent: STOR Power Ltd
Capacity Information:
De-Rated Capacity (Registry) 15.375
Connection/DSR Capacity 99.9
Anticipated Capacity 15.375
CMU: STPW36
Storage (Duration 2h) STOR 136 LTD Parent: STOR Power Ltd
Capacity Information:
De-Rated Capacity (Registry) 23.606
Connection/DSR Capacity 99.9
Anticipated Capacity 23.606