Land 260m to the southwest of Alness Grid Sub Station, Mid Balnacraig, Alness, Highlands, Scotland IV17 0YA
1 Component Storage (Duration 1.5h) BALNACRAIG BATTERY STORAGE LIMITED
Total Capacity: 4.78 MW
Components: 1
Technologies:
Storage (Duration 1.5h)
Unique CMUs: 1

Secondary Trading Contacts

Contact Information

Component Descriptions

Standalone Battery Storage on greenfield land near Alness substation

Used by 1 CMU

CMU Identifiers

Components at this Location

Standalone Battery Storage on greenfield land near Alness substation
CMU: BAL001
Storage (Duration 1.5h) BALNACRAIG BATTERY STORAGE LIMITED Parent: Intelligent Land Investments (Battery Storage) Limited
Capacity Information:
De-Rated Capacity (Registry) 4.781
Connection/DSR Capacity 41.5
Anticipated Capacity 4.954