Home List View Map View Technologies Companies Support Us Help Login Register
Theme
Land west of Blackpit Lane, Awbridge Farm, Lower Penn, Wolverhampton, Staffordshire, WV4 4YA
4 Components Storage (Duration 2h) PULSE CLEAN ENERGY SPV JOHNSON 1 LTD
Total Capacity: 27.31 MW
Components: 4
Technologies:
Storage (Duration 2h)
Unique CMUs: 2

Secondary Trading Contacts

Contact Information

Component Descriptions

New Build Battery Storage Site.

Used by 2 CMUs

CMU Identifiers

Components at this Location

New Build Battery Storage Site.
CMU: P12027
Storage (Duration 2h) PULSE CLEAN ENERGY SPV JOHNSON 1 LTD Parent: Pulse Clean Energy Ltd
Capacity Information:
De-Rated Capacity (Registry) 7.68
Connection/DSR Capacity 49.9
Anticipated Capacity 7.68
CMU: P32027
Storage (Duration 2h) PULSE CLEAN ENERGY SPV JOHNSON 3 LTD Parent: Pulse Clean Energy Ltd
Capacity Information:
De-Rated Capacity (Registry) 4.463
Connection/DSR Capacity 29
Anticipated Capacity 4.463