Search Map View Statistics Support Us Help Login Register
Land East of Feckenham Substation, Astwood Lane, Feckenham B96 6HP
2 Components Storage (Duration 6h) Storage (Duration 9h) LOGI ENERGY LIMITED
Total Capacity: 45.92 MW
Components: 2
Technologies:
Storage (Duration 6h), Storage (Duration 9h)
Unique CMUs: 2

Secondary Trading Contacts

Contact Information

Component Descriptions

New build BESS to be installed within a future Greener Grid Park.

Used by 2 CMUs

CMU Identifiers

Components at this Location

New build BESS to be installed within a future Greener Grid Park.
CMU: FECB-1
Storage (Duration 9h) LOGI ENERGY LIMITED Parent: Statkraft UK Ltd
Capacity Information:
De-Rated Capacity (Registry) 11.324
Connection/DSR Capacity 12
Anticipated Capacity 11.324
CMU: FECB-2
Storage (Duration 6h) LOGI ENERGY LIMITED Parent: Statkraft UK Ltd
Capacity Information:
De-Rated Capacity (Registry) 34.594
Connection/DSR Capacity 55.2
Anticipated Capacity 34.594