Tongland, Kirkcudbrightshire. DG6 4LT. Scotland
12 Components Hydro DRAX RIVER HYDRO LIMITED
Total Capacity: N/A
Components: 12
Technologies:
Hydro
Unique CMUs: 3

Secondary Trading Contacts

Contact Information

Component Descriptions

Tongland hydro power station - Unit 1 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.

Used by 3 CMUs

Tongland hydro power station - Unit 2 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.

Used by 3 CMUs

Tongland hydro power station - Unit 3 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.

Used by 3 CMUs

Components at this Location

Tongland hydro power station - Unit 1 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.
CMU: SP16TO
Capacity Information:
De-Rated Capacity (Registry) 29.761
Connection/DSR Capacity 34.541
CMU: SP17TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 30.368
Connection/DSR Capacity 34.541
Anticipated Capacity 30.368
CMU: SP18TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 31.177
Connection/DSR Capacity 34.607
Anticipated Capacity 31.177
Tongland hydro power station - Unit 2 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.
CMU: SP16TO
Capacity Information:
De-Rated Capacity (Registry) 29.761
Connection/DSR Capacity 34.541
CMU: SP17TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 30.368
Connection/DSR Capacity 34.541
Anticipated Capacity 30.368
CMU: SP18TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 31.177
Connection/DSR Capacity 34.607
Anticipated Capacity 31.177
Tongland hydro power station - Unit 3 Part of the Galloway hydroelectric scheme Registered capacity = 41.25MVA or 33MW at 0.8PF. Each of the 3 components = 11MW.
CMU: SP16TO
Capacity Information:
De-Rated Capacity (Registry) 29.761
Connection/DSR Capacity 34.541
CMU: SP17TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 30.368
Connection/DSR Capacity 34.541
Anticipated Capacity 30.368
CMU: SP18TO
Hydro DRAX RIVER HYDRO LIMITED Parent: Drax Hydro Limited
Capacity Information:
De-Rated Capacity (Registry) 31.177
Connection/DSR Capacity 34.607