High Flatworth, North Shields, Tyne and Wear, NE29 7SW
3 Components Storage (Duration 1h) PULSE CLEAN ENERGY UK LIMITED
Total Capacity: N/A
Components: 3
Technologies:
Storage (Duration 1h)
Unique CMUs: 3

Secondary Trading Contacts

Contact Information

Component Descriptions

New build one-hour duration storage to replace diesel plant

Used by 2 CMUs

One-hour duration battery storage project.

Used by 1 CMU

Components at this Location

New build one-hour duration storage to replace diesel plant
CMU: BATT09
Storage (Duration 1h) PULSE CLEAN ENERGY UK LIMITED Parent: Pulse Clean Energy Limited
Capacity Information:
De-Rated Capacity (Registry) 2.794
Connection/DSR Capacity 14
Anticipated Capacity 2.794
CMU: FW0011
Storage (Duration 1h) PULSE CLEAN ENERGY UK LIMITED Parent: Pulse Clean Energy Limited
Capacity Information:
De-Rated Capacity (Registry) 2.604
Connection/DSR Capacity 14
Anticipated Capacity 2.604
One-hour duration battery storage project.
CMU: FW2023
Storage (Duration 1h) PULSE CLEAN ENERGY UK LIMITED Parent: Pulse Clean Energy Limited
Capacity Information:
De-Rated Capacity (Registry) 1.814
Connection/DSR Capacity 16
Anticipated Capacity 1.814