Hazelside, Glespin, Lanark, Scotland, ML11 0RL - 13-turbine wind farm located in Lanark, Scotland with the installed capacity of 45.000MW

Component ID: DGWES2
Last updated: 16 Jul 2025 13:26 UTC

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 3.69 MW
  • De-Rated Capacity (CMU Registry) 3.03
  • Connection Capacity (CMU Registry) 45 MW
  • Anticipated Capacity (CMU Registry) 3.03 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name DOUGLAS WEST WIND FARM LTD
  • Parent Company (CMU Registry) Greencoat Uk Wind Holdco Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402070369682

Field Value
_id 584642
Type T-1
rank 0.0573088
CMU ID DGWES2
Auction Name 2023-24 (T-1) One Year Ahead Capacity Auction
Component ID T-DOUGW-1
Delivery Year 2023
De-Rated Capacity 3.69
OS Grid Reference NS 845 345
Proven DSR Capacity (empty)
Location and Post Code Hazelside, Glespin, Lanark, Scotland, ML11 0RL
Connection / DSR Capacity 45
Primary Fuel of Component (empty)
Generating Technology Class Onshore Wind
Description of CMU Components 13-turbine wind farm located in Lanark, Scotland with the installed capacity of 45.000MW
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13529
Type T-4
CMU ID DGWES2
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Douglas West wind farm
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Greencoat Uk Wind Holdco Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 3.033
Name of Applicant DOUGLAS WEST WIND FARM LTD
Primary Fuel Type Onshore Wind
Registered Holder DOUGLAS WEST WIND FARM LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 45
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2026-DGWES2-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 3.033
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 3.033
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4402070369682
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)