None - Location Barry Power Station is located to the south east of the town of Barry in the Vale of Glamorgan at national grid reference ST 14588 68516. The power station site occupies an area of approximately 1.7 hectares and is located on the eastern edge of the Barry Chemical Works complex comprising a variety of chemical works. The land on the opposite side of Sully Moors Road is zoned for industry. Beyond this is an area of low-lying open country. The nearest population centre is the town of Sully 1 km to the east south east of the installation. Plant One Gas Turbine and one Steam Turbine combined cycle design comprising: One Alsaldo V94.2 Gas Turbine with and ABB electrical generator; One Nooter Erikson Heat Recovery Steam Generator (HRSG); One Mitsubishi steam turbine with Brush electrical generator and air-cooled condenser; and Connection to the 132000 volt electrical distribution system. Metering Electrical Generation is MVRNd to the BRITGAS trading account. Site Works Power is netted off Total Generation to leave the balance as net export to the National Grid.

Component ID: EBRYP0
Last updated: 17 Jul 2025 09:19 UTC

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 0 MW
  • De-Rated Capacity (CMU Registry) 0
  • Connection Capacity (CMU Registry) 377.89 MW
  • Anticipated Capacity (CMU Registry) 0 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name Centrica plc
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) N/A

Field Value
_id 626573
Type T-4
rank 0.0706241
CMU ID EBRYP0
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
Component ID EBRYP0
Delivery Year 2018
De-Rated Capacity (empty)
OS Grid Reference (empty)
Proven DSR Capacity (empty)
Location and Post Code (empty)
Connection / DSR Capacity 377.89
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components Location Barry Power Station is located to the south east of the town of Barry in the Vale of Glamorgan at national grid reference ST 14588 68516. The power station site occupies an area of approximately 1.7 hectares and is located on the eastern edge of the Barry Chemical Works complex comprising a variety of chemical works. The land on the opposite side of Sully Moors Road is zoned for industry. Beyond this is an area of low-lying open country. The nearest population centre is the town of Sully 1 km to the east south east of the installation. Plant One Gas Turbine and one Steam Turbine combined cycle design comprising: One Alsaldo V94.2 Gas Turbine with and ABB electrical generator; One Nooter Erikson Heat Recovery Steam Generator (HRSG); One Mitsubishi steam turbine with Brush electrical generator and air-cooled condenser; and Connection to the 132000 volt electrical distribution system. Metering Electrical Generation is MVRNd to the BRITGAS trading account. Site Works Power is netted off Total Generation to leave the balance as net export to the National Grid.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity 131.419
Post-Refurbishing De-Rated Capacity 220
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 1887
Type T-4
CMU ID EBRYP0
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
CM Unit Name E_BRYP-1
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2018
Opt Out Status Opt-In
Opt-Out Reason N/A (Opt-in)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Refurbishing CMU
Storage Facility (empty)
De-Rated Capacity (empty)
Name of Applicant Centrica plc
Primary Fuel Type (empty)
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 377.89
Maximum Obligation Period 1
Capacity Agreement Awarded No
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status Refurbishing CM Unit only
Transmission / Distribution Distribution
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity (empty)
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status Refurbishing CM Unit only
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity 131.419
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity 220
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone (empty)
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity 131.419079
Anticipated Post-Refurbishing De-Rated Capacity 209
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)