None - The CMU DSR is formed by the load amanagement of the on site Fibre Preparation Plant. Metering arrangements (see separate description) will measure the net reduction resulting from an instruction to reduce output of the FPP Plant.

Component ID: ANLFPP
Last updated: 16 Jul 2025 14:17 UTC

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 3.59 MW
  • De-Rated Capacity (CMU Registry) 3.59
  • Connection Capacity (CMU Registry) 4 MW
  • Anticipated Capacity (CMU Registry) 3.59 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name Aylesford Newsprint Limited
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) N/A

Field Value
_id 626488
Type T-4
rank 0.0706241
CMU ID ANLFPP
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
Component ID ANLFPP
Delivery Year 2018
De-Rated Capacity 3.588
OS Grid Reference (empty)
Proven DSR Capacity (empty)
Location and Post Code (empty)
Connection / DSR Capacity 4
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components The CMU DSR is formed by the load amanagement of the on site Fibre Preparation Plant. Metering arrangements (see separate description) will measure the net reduction resulting from an instruction to reduce output of the FPP Plant.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 1807
Type T-4
CMU ID ANLFPP
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Aylesford Newsprint DSR - FPP
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR Yes
Delivery Year 2018
Opt Out Status Opt-In
Opt-Out Reason N/A (Opt-in)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required
CM Unit Category Unproven DSR CMU
Storage Facility (empty)
De-Rated Capacity 3.588
Name of Applicant Aylesford Newsprint Limited
Primary Fuel Type (empty)
Registered Holder Aylesford Newsprint Limited
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity 3.588
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5,000/MW
Termination Fee 2 Rate Β£25,000/MW
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 4
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2018-ANLFPP-00001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 3.588
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required
Pre-Refurbishment Bidding Status N/A
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2015-01-30
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 3.588
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone (empty)
Capacity Agreement has been Terminated Yes
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2018/2019
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement 2015-06-22
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)