LAND EAST OF LANGFORD MILL AND TYE FARM, LANGFORD, DEVON, EX15 2JY - Battery Storage

Component ID: LANF23
Last updated: 20 Jul 2025 13:05 UTC
CMU ID:
Primary Fuel:
Storage - Battery
Description:
Battery Storage
Auction:
2027-28 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 3.23 MW
  • De-Rated Capacity (CMU Registry) 3.23
  • Connection Capacity (CMU Registry) 21 MW
  • Anticipated Capacity (CMU Registry) 3.23 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name JBM SOLAR PROJECTS 2 LTD
  • Parent Company (CMU Registry) RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401793475215

Field Value
_id 140331
Type T-4
rank 0.0706241
CMU ID LANF23
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
Component ID LANF23
Delivery Year 2027
De-Rated Capacity 3.232
OS Grid Reference ST 036 032
Location and Post Code LAND EAST OF LANGFORD MILL AND TYE FARM, LANGFORD, DEVON, EX15 2JY
Connection / DSR Capacity 21
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 2h)
Description of CMU Components Battery Storage
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 14704
Type T-4
CMU ID LANF23
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
CM Unit Name CMU_LANF
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2027
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 3.232
Name of Applicant JBM SOLAR PROJECTS 2 LTD
Primary Fuel Type Storage - Battery
Registered Holder JBM SOLAR PROJECTS 2 LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 32320
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 21
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2027-LANF23-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 3.232
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required Yes
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2024-04-08
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 3.232
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401793475215
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042
Connection Agreement Deferral Declaration Yes
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2027-09-01
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2024-10-01
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement 2026-03-31
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2028-10-01