Farr Wind Farm, Garbole Road, Tomatin, Inverness, IV13 7ZA - This CMU component represent one half of Farr wind Farm.

Component ID: FarWF1
Last updated: 19 Jul 2025 18:19 UTC
CMU ID:
Technology:
Primary Fuel:
Onshore Wind
Description:
This CMU component represent one half of Farr wind Farm.
Auction:
2027-28 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 3.23 MW
  • De-Rated Capacity (CMU Registry) 6.11
  • Connection Capacity (CMU Registry) 92 MW
  • Anticipated Capacity (CMU Registry) 6.11 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name FARR WINDFARM LIMITED
  • Parent Company (CMU Registry) NADARA LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401312431380

Field Value
_id 281746
Type T-4
rank 0.0573088
CMU ID FarWF1
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
Component ID T_FARR-1
Delivery Year 2027
De-Rated Capacity 3.234
OS Grid Reference NH 701 294
Location and Post Code Farr Wind Farm, Garbole Road, Tomatin, Inverness, IV13 7ZA
Connection / DSR Capacity 46
Primary Fuel of Component Onshore Wind
Generating Technology Class Onshore Wind
Description of CMU Components This CMU component represent one half of Farr wind Farm.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 15544
Type T-4
CMU ID FarWF1
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Farr Wind Farm
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company NADARA LIMITED
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 6.108
Name of Applicant FARR WINDFARM LIMITED
Primary Fuel Type Onshore Wind
Registered Holder FARR WINDFARM LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 92
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2028-FarWF1-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 6.108
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 6.108
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401312431380
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2028/2029
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)