N/A Map

General Information

Key Details
  • Description Location Centrica Langage Power Station is a Combined Cycle Gas Turbine (CCGT) electricity generating station located on Eastern Wood Road on the outskirts of Plympton Devon at national grid reference SX 568 558. Plant Langage Energy Centre operates 2 Gas Turbines and one Steam Turbine in a combined cycle design comprising: 2 Alstom GT26B2.2 Gas Turbines with electrical generators (19KV); 2 Alstom Heat Recovery Steam Generators (HRSG); One Steam Turbine with electrical generator (21KV); One Air Cooled Condenser; Offsite gas Above Ground Installation (AGI) and 2.6km of gas pipeline owned and operated by Langage Energy Centre; 3 Step up Transformers (19/21KV – 400KV); and Connection to the 400KV volt electrical distribution system owned by National Grid though the Gas Insulated Substation. Metering Electrical Generation is MVRNd to the BRITGAS trading account. Site Works Power is netted off Total Generation to leave the balance as net export to the National Grid.
  • Auction 2018-19 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2018
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 796.40 MW
  • De-Rated Capacity (CMU Registry) 796.40
  • Connection Capacity (CMU Registry) 905 MW
  • Anticipated Capacity (CMU Registry) 796.40 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name EP Langage Limited
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) N/A

Field Value
_id 577786
Type T-4
rank 0.0706241
CMU ID TLAGA0
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
Component ID TLAGA0
Delivery Year 2018
De-Rated Capacity 796.4
OS Grid Reference
null
Proven DSR Capacity
null
Location and Post Code
null
Connection / DSR Capacity 905
Primary Fuel of Component
null
Generating Technology Class
null
Description of CMU Components Location Centrica Langage Power Station is a Combined Cycle Gas Turbine (CCGT) electricity generating station located on Eastern Wood Road on the outskirts of Plympton Devon at national grid reference SX 568 558. Plant Langage Energy Centre operates 2 Gas Turbines and one Steam Turbine in a combined cycle design comprising: 2 Alstom GT26B2.2 Gas Turbines with electrical generators (19KV); 2 Alstom Heat Recovery Steam Generators (HRSG); One Steam Turbine with electrical generator (21KV); One Air Cooled Condenser; Offsite gas Above Ground Installation (AGI) and 2.6km of gas pipeline owned and operated by Langage Energy Centre; 3 Step up Transformers (19/21KV – 400KV); and Connection to the 400KV volt electrical distribution system owned by National Grid though the Gas Insulated Substation. Metering Electrical Generation is MVRNd to the BRITGAS trading account. Site Works Power is netted off Total Generation to leave the balance as net export to the National Grid.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity 0
Post-Refurbishing De-Rated Capacity 0
Generating Capacity of on-site Generating Unit
null

Field Value
_id 2155
Type T-4
CMU ID TLAGA0
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
CM Unit Name T_LAGA-1
CM Unit Type CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2018
Opt Out Status Opt-In
Opt-Out Reason N/A (Opt-in)
Parent Company
null
DSR Test Method
null
Is FCM required
CM Unit Category Existing Generating CMU
Storage Facility
null
De-Rated Capacity 796.4
Name of Applicant EP Langage Limited
Primary Fuel Type
null
Registered Holder EP Langage Limited
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover
null
Termination Fee 1 Rate £5,000/MW
Termination Fee 2 Rate £25,000/MW
Termination Fee 3 Rate
null
Termination Fee 4 Rate
null
Termination Fee 5 Rate
null
Connection / DSR Capacity 905
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2018-TLAGA0-00001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 796.4
Term of the Capacity Agreement 1
Nature of the Security Interest First fixed charge over all rights in respect of the Capacity Agreement
CMU confirmed entry into Auction Yes
Is Connection Agreement required
Pre-Refurbishment Bidding Status N/A
Secondary Trading Contact - Email
null
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2015-01-30
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 796.4
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone
null
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2018/2019
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest Lloyds Bank PLC
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null