M74 Eco Park, Carlisle Road Lesmahagow ML11 0GU Map

General Information

Key Details
  • Description Load curtailment from on-site equipment in response to Flexitricity signal.
  • Auction 2028-29 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2028
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 7.99
  • Connection Capacity (CMU Registry) 10 MW
  • Anticipated Capacity (CMU Registry) 7.99 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name FLEXITRICITY LIMITED
  • Parent Company (CMU Registry) RESERVE POWER HOLDINGS (JERSEY) LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +441312218100

Field Value
_id 530529
Type T-4
rank 0.0573088
CMU ID F24191
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
Component ID 191001
Delivery Year 2028
De-Rated Capacity
null
OS Grid Reference NS 816 384
Location and Post Code M74 Eco Park, Carlisle Road Lesmahagow ML11 0GU
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class DSR
Description of CMU Components Load curtailment from on-site equipment in response to Flexitricity signal.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 15442
Type T-4
CMU ID F24191
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name FLEX191
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR Yes
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company RESERVE POWER HOLDINGS (JERSEY) LIMITED
DSR Test Method
null
Is FCM required
null
CM Unit Category Unproven DSR CMU
Storage Facility No
De-Rated Capacity 7.987
Name of Applicant FLEXITRICITY LIMITED
Primary Fuel Type DSR
Registered Holder FLEXITRICITY LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity 3.993
Amount of Credit Cover 39930
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 10
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2028-F24191-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 7.987
Term of the Capacity Agreement 15
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 3.993
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+441312218100
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042, 2042/2043
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement
null