Macketts Lane, Arreton, Isle of Wight PO30 3AS Map

General Information

Key Details
  • Description The CMU component will have a connection capacity of 7.5MW. Gas-fired reciprocating engine will be the technology used
  • Auction 2026-27 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2026
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 6.85 MW
  • De-Rated Capacity (CMU Registry) 6.85
  • Connection Capacity (CMU Registry) 7.50 MW
  • Anticipated Capacity (CMU Registry) 6.85 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name P3P KEYINGHAM LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) 2036676203

Field Value
_id 259799
Type T-4
rank 0.0573088
CMU ID MILL22
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
Component ID MILL1
Delivery Year 2026
De-Rated Capacity 6.851
OS Grid Reference SZ 543 840
Location and Post Code Macketts Lane, Arreton, Isle of Wight PO30 3AS
Connection / DSR Capacity 7.5
Primary Fuel of Component (empty)
Generating Technology Class Combined Heat and Power (CHP)
Description of CMU Components The CMU component will have a connection capacity of 7.5MW. Gas-fired reciprocating engine will be the technology used
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13894
Type T-4
CMU ID MILL22
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name MILL22
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 6.851
Name of Applicant P3P KEYINGHAM LIMITED
Primary Fuel Type Gas
Registered Holder P3P KEYINGHAM LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 102765
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 7.5
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2026-MILL22-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 6.851
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required Yes
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 6.851
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone 2036676203
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041
Connection Agreement Deferral Declaration Yes
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2025-08-31
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2025-05-31
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement 2025-03-31
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2027-10-01