Auchteraw Farm, Fort Augustus, PH32 4BT Map

General Information

Key Details
  • Description New build battery storage CMU with CMU ID 22AUC4
  • Auction 2026-27 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2026
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 7.55 MW
  • De-Rated Capacity (CMU Registry) 7.55
  • Connection Capacity (CMU Registry) 31.96 MW
  • Anticipated Capacity (CMU Registry) 7.55 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name FIELD AUCHTERAW LTD.
  • Parent Company (CMU Registry) V.E SERIES B BORROWER LTD
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407584073531

Field Value
_id 54417
Type T-4
rank 0.076422
CMU ID 22AUC4
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
Component ID 22AUC4
Delivery Year 2026
De-Rated Capacity 7.553
OS Grid Reference NH 347 076
Location and Post Code Auchteraw Farm, Fort Augustus, PH32 4BT
Connection / DSR Capacity 31.965
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 2h)
Description of CMU Components New build battery storage CMU with CMU ID 22AUC4
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13313
Type T-4
CMU ID 22AUC4
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name FIELD AUCHTERAW
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company V.E SERIES B BORROWER LTD
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 7.553
Name of Applicant FIELD AUCHTERAW LTD.
Primary Fuel Type Storage - Battery
Registered Holder FIELD AUCHTERAW LTD.
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 31.965
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2026-22AUC4-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 7.553
Term of the Capacity Agreement 15
Nature of the Security Interest 1.Debenture
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 7.553
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407584073531
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2025-04-10
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2023-09-16
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest 1.TP Leasing Limited
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2027-10-01