Land at Capenhurst Sub Station, Capenhurst, Cheshire, CH66 2HJ Map

General Information

Key Details
  • Description A New Build Battery Energy Storage System
  • Auction 2025-26 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2025
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 22.65
  • Connection Capacity (CMU Registry) 57 MW
  • Anticipated Capacity (CMU Registry) 22.65 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name HD888CAP LIMITED
  • Parent Company (CMU Registry) Pelagic Energy Development Ltd
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407973630171

Field Value
_id 223
Type T-4
rank 0.0706241
CMU ID CAPN25
Auction Name 2025-26 (T-4) Four Year Ahead Capacity Auction
Component ID CAPN25
Delivery Year 2025
De-Rated Capacity (empty)
OS Grid Reference SJ 367 749
Location and Post Code Land at Capenhurst Sub Station, Capenhurst, Cheshire, CH66 2HJ
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 2h)
Description of CMU Components A New Build Battery Energy Storage System
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 12508
Type T-4
CMU ID CAPN25
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2025-26 (T-4) Four Year Ahead Capacity Auction
CM Unit Name CAPENHURST
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Pelagic Energy Development Ltd
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 22.646
Name of Applicant HD888CAP LIMITED
Primary Fuel Type Storage - Battery
Registered Holder HD888CAP LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 57
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2025-CAPN25-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 22.646
Term of the Capacity Agreement 15
Nature of the Security Interest 1.Legal Interest
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2022-04-01
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 22.646
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407973630171
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2025/2026, 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest 1.Constantine Energy Storage LLP
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2026-10-01