General Information

Key Details
  • Description A Distribution Connected 4.5MW gas fueled generating station
  • Auction 2025-26 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2025
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 4.75 MW
  • De-Rated Capacity (CMU Registry) 4.75
  • Connection Capacity (CMU Registry) 5.08 MW
  • Anticipated Capacity (CMU Registry) 4.21 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name SUNCROP BURSTWICK GENERATION LIMITED
  • Parent Company (CMU Registry) Suncrop Generation Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407764281842

Field Value
_id 530982
Type T-1
rank 0.0573088
CMU ID BRGP25
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
Component ID BurstwickGP
Delivery Year 2025
De-Rated Capacity 4.748
OS Grid Reference TA 225 284
Location and Post Code Ellifoot Lane, Burstwick, HU12 9EB
Connection / DSR Capacity 5.079
Primary Fuel of Component Gas
Generating Technology Class Reciprocating engines
Description of CMU Components A Distribution Connected 4.5MW gas fueled generating station
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 11942
Type T-1
CMU ID BRGP25
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
CM Unit Name Burstwick GP
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Suncrop Generation Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 4.748
Name of Applicant SUNCROP BURSTWICK GENERATION LIMITED
Primary Fuel Type Gas
Registered Holder SUNCROP BURSTWICK GENERATION LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 5.079
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2025-BRGP25-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 4.207
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 4.748
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407764281842
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2025/2026
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2025-09-30
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2024-12-01
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement 2025-10-01