Home List View Map View Technologies Companies Support Us Help Login Register
Theme
Land at Monk Fryston Substation, Rawfield Lane, Leeds, LS25 5JD Map

General Information

Key Details
  • Description A New Build Gas fuelled power plant
  • Auction 2024-25 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2024
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 47.52
  • Connection Capacity (CMU Registry) 49.90 MW
  • Anticipated Capacity (CMU Registry) 47.52 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name HD777FRY LTD
  • Parent Company (CMU Registry) Pelagic Energy Development Ltd
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407973630171

Field Value
_id 366627
Type T-4
rank 0.0706241
CMU ID FRY024
Auction Name 2024-25 (T-4) Four Year Ahead Capacity Auction
Component ID FRY024
Delivery Year 2024
De-Rated Capacity (empty)
OS Grid Reference SE 485 289
Location and Post Code Land at Monk Fryston Substation, Rawfield Lane, Leeds, LS25 5JD
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Reciprocating engines
Description of CMU Components A New Build Gas fuelled power plant
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 11420
Type T-4
CMU ID FRY024
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2024-25 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Fryston
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2024
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Pelagic Energy Development Ltd
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 47.515
Name of Applicant HD777FRY LTD
Primary Fuel Type Gas
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 475150
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 49.9
Maximum Obligation Period 15
Capacity Agreement Awarded (empty)
Pre-Qualification Decision Not Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 47.515
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction (empty)
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407973630171
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)