Home List View Map View Technologies Companies Support Us Help Login Register
Theme
Pye Bridge Industrial Estate, Somercotes, Alfreton, DE55 4NX Map

General Information

Key Details
  • Description Additional reciprocating gas engines running on natural gas returned to service
  • Auction 2024-25 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2024
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 2.25
  • Connection Capacity (CMU Registry) 2.38 MW
  • Anticipated Capacity (CMU Registry) 2.25 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name PYEBRIDGE POWER LTD
  • Parent Company (CMU Registry) SLOANE DEVELOPMENTS LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +447572438654

Field Value
_id 535301
Type ST
rank 0.0706241
CMU ID MAP23A
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
Component ID MAP23A
Delivery Year 2024
De-Rated Capacity 2.25
OS Grid Reference SK 433 530
Location and Post Code Pye Bridge Industrial Estate, Somercotes, Alfreton, DE55 4NX
Connection / DSR Capacity 2.385
Primary Fuel of Component Gas
Generating Technology Class Reciprocating engines
Description of CMU Components Additional reciprocating gas engines running on natural gas returned to service
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10749
Type ST
CMU ID MAP23A
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
CM Unit Name MAP23A Additional Capacity due to returned engine
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2024
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company SLOANE DEVELOPMENTS LIMITED
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 2.25
Name of Applicant PYEBRIDGE POWER LTD
Primary Fuel Type Gas
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 2.385
Maximum Obligation Period 1
Capacity Agreement Awarded (empty)
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 2.25
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction (empty)
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+447572438654
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)