Alne Material Recovery Facility, Forest Lane, Alne, York, YO61 1TU Map

General Information

Key Details
  • Description New Build Generating CMU comprising of a CHP asset producing energy from waste.
  • Auction 2024-25 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2024
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 0.89
  • Connection Capacity (CMU Registry) 1 MW
  • Anticipated Capacity (CMU Registry) 0.89 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name ALLIUM HELMSLEY LTD
  • Parent Company (CMU Registry) Allium Helmsley Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401347833294

Field Value
_id 149932
Type T-1
rank 0.0706241
CMU ID ALLHM4
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
Component ID ALLHM4
Delivery Year 2024
De-Rated Capacity 0.885
OS Grid Reference SE 521 663
Location and Post Code Alne Material Recovery Facility, Forest Lane, Alne, York, YO61 1TU
Connection / DSR Capacity 1
Primary Fuel of Component Waste
Generating Technology Class Energy from Waste
Description of CMU Components New Build Generating CMU comprising of a CHP asset producing energy from waste.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10468
Type T-1
CMU ID ALLHM4
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
CM Unit Name Alne (EFW)
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2024
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Allium Helmsley Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 0.885
Name of Applicant ALLIUM HELMSLEY LTD
Primary Fuel Type Waste
Registered Holder ALLIUM HELMSLEY LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 1
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2024-ALLHM4-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 0.885
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2024-04-02
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 0.885
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401347833294
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2024/2025
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2023-09-29
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved 2023-08-14
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)