Home List View Map View Technologies Companies Support Us Help Login Register
Theme
Whitfire Shavings and Sawdust Supplies Ltd, Heatherfield Works, Church Lane, Farington, Nr Preston, PR26 6RD Map

General Information

Key Details
  • Description CHP Unit
  • Auction 2023-24 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2023
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 1.18
  • Connection Capacity (CMU Registry) 1.29 MW
  • Anticipated Capacity (CMU Registry) 1.18 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name ENEL X UK LIMITED
  • Parent Company (CMU Registry) ENEL X INTERNATIONAL S.R.L.
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402037954936

Field Value
_id 366414
Type ST
rank 0.0573088
CMU ID ZGEN15
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
Component ID ZGEN15B
Delivery Year 2023
De-Rated Capacity (empty)
OS Grid Reference SD 536 250
Location and Post Code Whitfire Shavings and Sawdust Supplies Ltd, Heatherfield Works, Church Lane, Farington, Nr Preston, PR26 6RD
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Combined Heat and Power (CHP)
Description of CMU Components CHP Unit
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10434
Type ST
CMU ID ZGEN15
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
CM Unit Name ZGEN15
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2023
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company ENEL X INTERNATIONAL S.R.L.
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 1.183
Name of Applicant ENEL X UK LIMITED
Primary Fuel Type Gas
Registered Holder ENEL X UK LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 1.295
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2023 - 21/04/2024:0.000 MW; 22/04/2024 - 30/09/2024:1.183 MW
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2023-ZGEN15-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 1.183
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction (empty)
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2024-04-19
List of Traded Capacity Obligations T1: 1.183 MW
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies T1: 22/04/2024 - 30/09/2024
Secondary Trading Contact - Telephone '+4402037954936
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2023/2024
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)